Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Shreeram Shreeyansh Park RERA Details - P52100019134, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Shreeram Shreeyansh Park under registration P52100019134 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100019134
  • Project Name SHREEYANSH PARK
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Pimpri Chinchawad (M Corp.)
  • Original Completion 30 September 2020
  • Revised Completion 30 June 2026
  • Project Area (in Sq.mt.) 932.92
  • Total Buildings/Towers 1
  • Documents 38 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 January 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 September 2020 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SHRIRAM DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
RAHUL GORAKH YADAVPartnerPune, MAHARASHTRA
BALU DAMODAR TAPKIRPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SHREEYANSH PARK SHREEYANSH PARK 0 15 5 4 4 25 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 24
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 24 units · avg area 36.41 Sq.mt.
  • SHREEYANSH PARK
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 24.4 2 0
1BHK 24.69 2 0
1BHK 37.18 4 1
1BHK 38.48 4 0
1BHK 38.7 4 0
1BHK 39.18 2 0
1BHK 39.69 1 1
1BHK 39.75 1 0
1BHK 40.4 2 0
1BHK 39.87 2 2
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SHREEYANSH PARK
SHREEYANSH PARK · Overall Progress 82%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 2 Copy Of Layout Approval (In Case Of Layout).Pdf
6 3 Copy Of Layout Approval (In Case Of Layout).Pdf
7 4 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval (IOD).Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 2 Commencement Certificates NA Order For Plotted Development.Pdf
11 1 Declaration In FORM B.Pdf
12 1 Certificates Of CA (Form 3).Pdf
13 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
14 1 Proforma Of Allotment Letter.Pdf
15 2 Proforma Of Allotment Letter.Pdf
16 Form 1.Pdf
17 Form 2.Pdf
18 Form 3.Pdf
19 Disclosure Of Sold And Booked Inventory.Pdf
107 Withdrawal Update Form 1.Pdf
111 Withdrawal Update Form 2.Pdf
112 Withdrawal Update Form 3.Pdf
116 Form 2A (FY 2018 2019).Pdf
117 Form 2A (FY 2019 2020).Pdf
118 Form 2A (FY 2020 2021).Pdf
119 Form 2A (FY 2021 2022).Pdf
120 Form 2A (FY 2023 2024).Pdf
121 Form 2A (FY 2022 2023).Pdf
122 Form 2A (FY 2024 2025).Pdf
123 Form 5 (FY 2019 2020).Pdf
124 Form 5 (FY 2020 2021).Pdf
125 Form 5 (FY 2021 2022).Pdf
126 Form 5 (FY 2022 2023).Pdf
127 Form 5 (FY 2023 2024).Pdf
128 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000437
Branch Address KAMALA CROSSROAD, PCMC OFFICE, PIMPRI - 411017
Country/City