residential Partially Ready To Move Source: rera.mh

SOL The Address Phase 3 RERA Details - P52100020839, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for SOL The Address Phase 3 under registration P52100020839 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100020839
  • Project Name THE ADDRESS PHASE-3
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Pimpri Chinchawad (M Corp.)
  • Original Completion 28 November 2023
  • Revised Completion 28 November 2023
  • Project Area (in Sq.mt.) 6,459.52
  • Total Buildings/Towers 3
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 15 May 2019 Expected commencement of civil works and foundation on site.
Original Completion 28 November 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 28 November 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name SOL Developers
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
THE ADDRESS-1gat no 519 520 Pune Nashik Road moshi6750.5CompletedResidential / Group Housing3122019-11-302019-04-11NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
THE ADDRESS PHASE-3 I 38 32 13 0 0 NA
THE ADDRESS PHASE-3 F 36 34 14 0 0 NA
THE ADDRESS PHASE-3 G 6 20 14 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 282
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 94 units · avg area 37.08 Sq.mt.
2 BHK 142 units · avg area 47.26 Sq.mt.
3 BHK 1 unit · avg area 69.27 Sq.mt.
5 BHK 45 units · avg area 58.51 Sq.mt.
  • I
  • F
  • G
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3BHK 69.27 1 0
2BHK 55.03 1 0
2.5 BHK 60.19 21 13
2.5 BHK 57.09 22 3
2 BHK 49.74 23 14
2 BHK 50.0 23 13
2 BHK 50.96 1 1
2.5 BHK 56.48 2 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 70.0% Water Supply 60.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 75.0%
Storm Water Drains 60.0% Landscaping & Tree Planting 60.0% Street Lighting 60.0%
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 60.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 70.0%
Electrical Meter Room, Sub-station, Receiving Station 70.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • I
  • F
  • G
I · Overall Progress 73%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank INDUSIND BANK
IFSC INDB0000006
Branch Address Induslnd Bnak Ltd,Gr Floor,Atlanta Building,Mumbai-400021
Country/City