RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100019978
- Project Name TANISH PEARLS PHASE 1
- Project Type Others
- Project Status Ready to Move
- State MAHARASHTRA
- District Pune
- Taluka Haveli
- Village CHARHOLI
- Original Completion 30 December 2025
- Project Area (in Sq.mt.) 7,828.29
- Total Buildings/Towers 5
- Documents 37 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| Dilip Shantilal Solanki | Authorized Signatory |
| Shrenik Nirmal Parmar | Partner |
| Raju Mohanlal Mehta | Partner |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| TANISH PEARLS PHASE 1 | A BUILDING | 2024-12-31 | 0 | 1 | 0 | 14 | 1 | 0 | 35 |
| TANISH PEARLS PHASE 1 | B BUILDING | 2024-12-31 | 0 | 1 | 0 | 14 | 1 | 0 | 35 |
| TANISH PEARLS PHASE 1 | C BUILDING | 2024-12-31 | 0 | 1 | 0 | 14 | 1 | 0 | 0 |
| TANISH PEARLS PHASE 1 | D BUILDING | 2024-12-31 | 0 | 1 | 0 | 14 | 1 | 0 | 0 |
| TANISH PEARLS PHASE 1 | E BUILDING | 2024-12-31 | 0 | 1 | 0 | 14 | 1 | 0 | 0 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- A BUILDING
- B BUILDING
- C BUILDING
- D BUILDING
- E BUILDING
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| FLAT 1 BHK | 27.43 | 11 | 11 |
| FLAT 1 BHK | 32.41 | 12 | 12 |
| FLAT 2 BHK | 34.25 | 23 | 23 |
| FLAT 2 BHK | 39.17 | 24 | 24 |
| FLAT 1 BHK | 32.32 | 12 | 12 |
| FLAT 1 BHK | 27.51 | 12 | 12 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2BHK | 34.25 | 24 | 24 |
| 1BHK | 32.41 | 11 | 11 |
| 1BHK | 32.32 | 12 | 12 |
| 1BHK | 27.51 | 12 | 12 |
| 1BHK | 27.43 | 12 | 12 |
| 2BHK | 39.17 | 23 | 22 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1 BHK | 27.51 | 12 | 12 |
| 1 BHK | 32.32 | 12 | 12 |
| 1 BHK | 32.41 | 12 | 12 |
| 2 BHK | 39.17 | 24 | 24 |
| 1 BHK | 27.43 | 11 | 11 |
| 2 BHK | 34.25 | 23 | 21 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| FLAT 1 BHK | 27.43 | 12 | 12 |
| FLAT 1 BHK | 27.51 | 12 | 12 |
| FLAT 1 BHK | 32.41 | 11 | 11 |
| FLAT 2 BHK | 34.25 | 24 | 24 |
| FLAT 2 BHK | 39.17 | 23 | 23 |
| FLAT 1 BHK | 32.32 | 12 | 12 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| FLAT 1 BHK | 27.43 | 11 | 11 |
| FLAT 1 BHK | 27.51 | 12 | 12 |
| FLAT 1 BHK | 32.32 | 12 | 12 |
| FLAT 1 BHK | 32.41 | 12 | 12 |
| 2BHK | 39.17 | 24 | 24 |
| 2 BHK | 34.25 | 23 | 22 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 0 | 0 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 100% | Water Conservation Rainwater Harvesting 100% | Energy Management 100% |
| Fire Protection And Fire Safety Requirements 100% | Electrical Meter Room Substation Receivingstation 100% | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking % not reported | Water Supply 100% | Sewerage 100% |
| Storm Water Drains 100% | Landscaping Tree Planting 100% | Street Lighting 100% |
| Community Buildings 100% | Treatment And Disposal Of Sewage Sullage Water 20% | Solid Waste Management Disposal 100% |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- A BUILDING
- B BUILDING
- C BUILDING
- D BUILDING
- E BUILDING
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | STATE BANK OF INDIA |
|---|---|
| IFSC | SBIN0004108 |