Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Triaa Saachee Era RERA Details - P52100015810, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Triaa Saachee Era under registration P52100015810 in Pune, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100015810
  • Project Name SAACHEE ERA
  • Project Type Others
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Pune
  • Taluka Haveli
  • Village Pimpri Chinchawad (M Corp.)
  • Original Completion 31 December 2019
  • Project Area (in Sq.mt.) 2,450
  • Total Buildings/Towers 1
  • Documents 23 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 26 March 2018 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2019 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Saachee Group and Superior Spaces
Other Description NA

Promoters, Co-promoters & Members

NameRole
SHYAMLAL PATIRAM GOELAuthorized Signatory
GAURAV NARENDRA SALUNKHEPartner

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
SAACHEE ERA SAACHEE ERA 2019-12-31 1 1 0 13 0 25 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 80
Configurations 11
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 68 units · avg area 77.76 Sq.mt.
FLAT 101 1 unit · avg area 113.75 Sq.mt.
SHOP NO 101 1 unit · avg area 87.51 Sq.mt.
FLAT 105 1 unit · avg area 94.24 Sq.mt.
FLAT 201 1 unit · avg area 109.75 Sq.mt.
FLAT 207 1 unit · avg area 116.69 Sq.mt.
Ground Floor SHOP 1 unit · avg area 23.96 Sq.mt.
Office space 1 unit · avg area 23.51 Sq.mt.
Shop First Floor 2 units · avg area 27.94 Sq.mt.
SHOP FIRST FLOOR 2 units · avg area 21.04 Sq.mt.
Shop 1 unit · avg area 23.51 Sq.mt.
  • SAACHEE ERA
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2 BHK TYPE 1 73.4 21 21
2 BHK TYPE 2 76.64 19 19
2 BHK TYPE 3 78.96 11 11
FLAT 105 94.24 1 1
Ground Floor SHOP 23.96 1 0
Office space 23.51 1 0
FLAT 101 113.75 1 0
2 BHK TYPE 4 83.61 17 17
Shop First Floor 27.94 2 2
SHOP FIRST FLOOR 21.04 2 0
Shop 23.51 1 0
FLAT 207 116.69 1 1
FLAT 201 109.75 1 1
SHOP NO 101 87.51 1 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage NA NA 0
Covered Parking 26 23 100
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths % not reported Water Conservation Rainwater Harvesting 100% Energy Management 100%
Fire Protection And Fire Safety Requirements 100% Electrical Meter Room Substation Receivingstation 100% Aggregate Area Of Recreational Open Space 100%
Open Parking 100% Water Supply 100% Sewerage 100%
Storm Water Drains 100% Landscaping Tree Planting 50% Street Lighting 50%
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water 50% Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SAACHEE ERA
SAACHEE ERA · Overall Progress 98%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Complete
% Work100%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work95%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
In Progress
% Work95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
In Progress
% Work95%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work95%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
2 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
1 Disclosure Of Sold/ Booked Inventory
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020-21)
1 Proforma Of Allotment Letter
2 Proforma Of Allotment Letter
3 Proforma Of Allotment Letter
1 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Kotak Mahindra Bank Ltd
IFSC KKBK0000730
Country/City