Unique Flow Kiwale RERA Details - P52100051788, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Unique Flow Kiwale under registration P52100051788 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100051788
  • Project Name FLOW KIWALE
  • Project Type Commercial
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Pimpri Chinchawad (M Corp.)
  • Original Completion 31 March 2026
  • Revised Completion 31 March 2026
  • Project Area (in Sq.mt.) 2,619.45
  • Total Buildings/Towers 1
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 03 July 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 March 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name UNIQUE AMS SPACES LLP

Promoters, Co-promoters & Members

NameRoleAddress
SUMIT SUBHASH TAYALPartnerPune, MAHARASHTRA
SUBHASH RAMKISAN TAYALPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
FLOW KIWALE Flow Kiwale 0 0 2 1 1 25 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 25
Configurations 1
Inventory Type COMMERCIAL
Configuration Distribution
Showroom 25 units · avg area 63.77 Sq.mt.
  • Flow Kiwale
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Showroom 27.64 1 1
Showroom 53.4 5 5
Showroom 38.52 1 1
Showroom 273.38 1 1
Showroom 27.55 1 1
Showroom 49.0 1 1
Showroom 133.63 1 0
Showroom 92.46 2 1
Showroom 49.43 1 1
Showroom 52.2 4 4
Showroom 53.76 1 1
Showroom 25.6 1 1
Showroom 54.24 3 3
Showroom 38.77 1 1
Showroom 53.43 1 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 95.0%
Storm Water Drains 95.0% Landscaping & Tree Planting 60.0% Street Lighting 50.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 75.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 50.0%
Electrical Meter Room, Sub-station, Receiving Station 70.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Flow Kiwale
Flow Kiwale · Overall Progress 32%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work80%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work20%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
51 Withdrawal Update Form 1.Pdf
57 Withdrawal Update Form 2.Pdf
63 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank KOTAK MAHINDRA BANK LIMITED
IFSC KKBK0001769
Branch Address FC Road, Pune