RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100015026
- Project Name OXY FLORA
- Project Type Residential
- Project Status Partially Ready To Move
- State MAHARASHTRA
- District Pune
- Taluka Haveli
- Village Loni-kand
- Original Completion 31 December 2020
- Revised Completion 30 June 2021
- Project Area (in Sq.mt.) 4,314.64
- Total Buildings/Towers 1
- Documents 93 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
| Project Name | Address | Land Area | Type of Project | Build Plot Count | Apartment count | Project End Date |
|---|---|---|---|---|---|---|
| OXY FLORA | GAT NO 403 SIDDHI CERAMICS LONIKAND TAL-HAVELI DIST PUNE | 4314.64 | Residential | 1 | 0 | 2020-12-31 |
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| YOGESH PANDIT GAWALI | Partner |
| RAHUL KONDIBA SATAV | Authorized Signatory |
| SANDEEP KONDIBA SATAV | Partner |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| OXY FLORA | B | 2020-12-31 | 0 | 1 | 0 | 10 | 0 | 65 | 0 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- B
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 1BHK | 29.01 | 4 | 4 |
| 2BHK | 38.63 | 4 | 4 |
| 1 BHK | 27.68 | 4 | 4 |
| 1BHK | 26.27 | 4 | 4 |
| 2 BHK | 40.47 | 4 | 4 |
| 1 BHK | 26.24 | 8 | 8 |
| 1 BHK | 29.77 | 4 | 4 |
| 1 BHK LANDOWNER | 26.12 | 1 | 0 |
| 1BHK | 27.72 | 6 | 6 |
| 1 BHK LANDOWNER | 27.72 | 1 | 0 |
| 2BHK | 38.67 | 3 | 3 |
| 2 BHK LANDOWNER | 38.67 | 1 | 0 |
| 1BHK | 24.03 | 7 | 7 |
| 1BHK LANDOWNER | 24.03 | 1 | 0 |
| 2BHK | 37.24 | 2 | 2 |
| 2BHK LANDOWNER | 37.24 | 2 | 0 |
| 2BHK | 43.5 | 2 | 2 |
| 2BHK LANDOWNER | 43.5 | 2 | 0 |
| 2BHK | 37.41 | 3 | 3 |
| 2 BHK LANDOWNER | 37.41 | 1 | 0 |
| 2BHK | 41.32 | 6 | 6 |
| 2 BHK LANDOWNER | 41.32 | 2 | 0 |
| 1 BHK | 25.81 | 8 | 8 |
| 1 BHK | 26.76 | 4 | 4 |
| 1 BHK | 28.36 | 8 | 8 |
| 1BHK | 26.12 | 3 | 3 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 75 | 75 | 100 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 100% | Water Conservation Rainwater Harvesting 100% | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements 90% | Electrical Meter Room Substation Receivingstation 90% | Aggregate Area Of Recreational Open Space 100% |
| Open Parking 100% | Water Supply 100% | Sewerage 75% |
| Storm Water Drains 100% | Landscaping Tree Planting 100% | Street Lighting 100% |
| Community Buildings 100% | Treatment And Disposal Of Sewage Sullage Water 60% | Solid Waste Management Disposal 60% |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- B
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | STATE BANK OF INDIA |
|---|---|
| IFSC | SBIN0001110 |