Ashar Edge RERA Details - P51700016015, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Ashar Edge under registration P51700016015 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700016015
  • Project Name ASHAR EDGE WING A PHASE II
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 30 October 2023
  • Revised Completion 30 October 2023
  • Project Area (in Sq.mt.) 5,194.73
  • Total Buildings/Towers 1
  • Documents 35 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 11 April 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 October 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 October 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name Ms ASHAR VENTURES
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
ASHAR SAPPHIRE AND GALLERIAGUT NO 32-2G AND 32-1-6 SUB PLOT B VILLAGE CHITALSAR MANPADA THANE4638.1CompletedIndustrial12062021-12-302021-12-30NoNA

Promoters, Co-promoters & Members

NameAddress
AJAY ASHARThane, MAHARASHTRA
MAX MOTORS PRIVATE LIMITEDThane, MAHARASHTRA
TOSCANO INFRASTRUCTURE PRIVATE LIMITEDThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
ASHAR EDGE WING A PHASE II RESIDENTIAL WING A PHASE II 0 200 38 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 183
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 66 units · avg area 36.12 Sq.mt.
2 BHK 117 units · avg area 55.25 Sq.mt.
  • RESIDENTIAL WING A PHASE II
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2 BHK TYPE 3 55.25 117 114
1 BHK TYPE 2 35.92 64 63
1 BHK TYPE 1 42.4 2 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Solar Powered Water Heating % not reported Star Gazing Deck % not reported Swimming Pool % not reported
Turf Cricket Pitch % not reported Use Of Energy Efficient Light Fixtures % not reported Use Of Heat Resistance Paints % not reported
Use Of Low Flow Water Faucets And Dual Flush % not reported Video Door Phones % not reported Wifi Access Enabled For Common Areas % not reported
Sky Lounge % not reported Skating Rink % not reported Senior Citizen Corner % not reported
Rain Water Harvesting % not reported Provision Of Smart Access Card Rfid Biometrics % not reported Provision Of Ip Based Cctv Cameras % not reported
Outdoor Play Area % not reported Odourless Paints With Lower Vocs % not reported Multipurpose Room As Banquet Hall % not reported
Multipurpose Court % not reported Multi Tv Dish Tv Connection Plug And Play % not reported Multi Purpose Room As Guest Room % not reported
Kitched Garden % not reported High Performance Glazing % not reported Gas And Smoke Detectors In Each Kitchen % not reported
Electric Charging Facility For Vehicles % not reported Boom Barrier Security Gate % not reported Automatic Sensors For Common Enclosed Amenity Areas % not reported
Addressable Fire Zone Detection System % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • RESIDENTIAL WING A PHASE II
RESIDENTIAL WING A PHASE II · Overall Progress 96%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
In Progress
% Work90%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work95%
Sanitary Fittings within the flats / premises
In Progress
% Work90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
Mh Certificate Pdf
Mh Details Html
3 1 Details Of Encumbrances.Pdf
4 2 Details Of Encumbrances.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 2 Copy Of Layout Approval (In Case Of Layout).Pdf
7 1 Building Plan Approval (IOD).Pdf
8 2 Building Plan Approval (IOD).Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 2 Commencement Certificates NA Order For Plotted Development.Pdf
11 3 Commencement Certificates NA Order For Plotted Development.Pdf
12 4 Commencement Certificates NA Order For Plotted Development.Pdf
13 5 Commencement Certificates NA Order For Plotted Development.Pdf
14 6 Commencement Certificates NA Order For Plotted Development.Pdf
15 1 Declaration In FORM B.Pdf
16 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
17 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
18 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
19 1 Certificates Of CA (Form 3).Pdf
20 2 Certificates Of CA (Form 3).Pdf
21 3 Certificates Of CA (Form 3).Pdf
22 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
23 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
24 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
25 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
26 1 Proforma Of Allotment Letter.Pdf
27 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
28 2 Architect’S Certificate On Completion Of Project (Form 4).Pdf
29 1 Status Of Formation Of Legal Entity (Society Co Op Etc.).Pdf
30 1 Other.Pdf
31 2 Other.Pdf
32 3 Other.Pdf
33 4 Other.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.