Cosmos Horizon Phase 2 RERA Details - P51700017557, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Cosmos Horizon Phase 2 under registration P51700017557 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700017557
  • Project Name COSMOS HORIZON PHASE II
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 30 March 2024
  • Revised Completion 30 March 2024
  • Project Area (in Sq.mt.) 476.59
  • Total Buildings/Towers 2
  • Documents 48 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 28 August 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 March 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 March 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Concorde Developers

Promoters, Co-promoters & Members

NameRoleAddress
Pradeep Ghisulal RathodPartnerMumbai City, MAHARASHTRA
Pankaj Ghisulal RathodPartnerMumbai City, MAHARASHTRA
Sanjay Chandan ParekhPartnerMumbai City, MAHARASHTRA
Cosmos Skyline Homes Pvt Ltd Cosmos Skyline Homes Pvt LtdPartnerMumbai City, MAHARASHTRA
Cosmos Prime Projects Ltd Cosmos Prime Projects LtdPartnerMumbai City, MAHARASHTRA
Manish Gyanchand MehtaPartnerN5BGVWCbvD5UEgvR2rv3D1dGZrIwxp2mGqXIAewvbInmjxYxORxwpiTfCuRTpAbc, Mumbai City, MAHARASHTRA
Suresh Yedba JantrePartnerOsmanabad, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
COSMOS HORIZON PHASE II BUILDING 5 SUNLITE 7 167 30 0 0 NA
COSMOS HORIZON PHASE II BUILDING 6 MOONLITE 7 1 30 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING 5 SUNLITE
  • BUILDING 6 MOONLITE
BUILDING 5 SUNLITE · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

40 2 Other.Pdf
41 3 Other.Pdf
Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 2 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval (IOD).Pdf
7 1 Commencement Certificates NA Order For Plotted Development.Pdf
8 2 Commencement Certificates NA Order For Plotted Development.Pdf
9 1 Declaration About Commencement Certificate.Pdf
10 1 Declaration In FORM B.Pdf
11 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
12 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
13 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
14 4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
15 5 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
16 6 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
17 7 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
18 8 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
19 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
20 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
21 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
22 1 Disclosure Of Sold Booked Inventory.Pdf
23 1 CERSAI Details.Pdf
24 1 Certificates Of CA (Form 3).Pdf
25 2 Certificates Of CA (Form 3).Pdf
26 3 Certificates Of CA (Form 3).Pdf
27 4 Certificates Of CA (Form 3).Pdf
28 5 Certificates Of CA (Form 3).Pdf
29 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
30 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
31 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
32 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
33 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
34 1 Proforma Of Allotment Letter.Pdf
35 2 Proforma Of Allotment Letter.Pdf
36 3 Proforma Of Allotment Letter.Pdf
37 1 Details Of Restarting Of Construction Work Post Lockdown.Pdf
38 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
39 1 Other.Pdf
42 4 Other.Pdf
43 5 Other.Pdf
44 6 Other.Pdf
45 7 Other.Pdf
49 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0000509
Branch Address GEORGE MANSION, UTALSAR, THANE WEST - 400601
Country/City