D V Shree Shashwat RERA Details - P51700055631, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for D V Shree Shashwat under registration P51700055631 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700055631
  • Project Name SHREE SHASHWAT BUILDING NO. 21
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Mira-Bhayandar (M Corp.)
  • Original Completion 14 January 2027
  • Revised Completion 14 January 2027
  • Project Area (in Sq.mt.) 292.75
  • Total Buildings/Towers 1
  • Documents 40 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 05 April 2024 Expected commencement of civil works and foundation on site.
Original Completion 14 January 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 14 January 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name G N DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
MUKESH JUHARMAL PARMARPartnerMumbai City, MAHARASHTRA
RAJENDRA KUMAR BHAGAWATIPRASAD SHARMAPartnerMumbai Suburban, MAHARASHTRA
SANTOSH MANSARAM PATILPartnerThane, MAHARASHTRA
PIYUSHKUMAR BABULAL JAINPartnerMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SHREE SHASHWAT BUILDING NO. 21 BLDG NO C 9 51 23 22 22 85 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 85
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 41 units · avg area 40.42 Sq.mt.
2 BHK 44 units · avg area 55.58 Sq.mt.
  • BLDG NO C
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 39.99 19 5
1BHK 40.79 22 1
2BHK 55.58 44 6
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 20.0%
Electrical Meter Room, Sub-station, Receiving Station 80.0% Aggregate Area Of Recreational Open Space 20.0% Open Parking 80.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BLDG NO C
BLDG NO C · Overall Progress 64%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work82%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work42%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 B Details Of Encumbrances Concerned To Legal.Pdf
6 2 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval NA Order For Plotted Development.Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 1 Declaration About Commencement Certificate.Pdf
11 1 Declaration In FORM B.Pdf
12 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
14 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
15 1 CERSAI Details.Pdf
16 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
17 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
18 1 Proforma Of Agreement For Sale.Pdf
19 1 Proforma Of Allotment Letter.Pdf
20 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
21 1 Deviation Report With Respect To Allotment Letter.Pdf
22 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
23 1 Other – Legal.Pdf
24 1 Other – Technical.Pdf
25 2 Other – Technical.Pdf
26 3 Other – Technical.Pdf
27 4 Other – Technical.Pdf
33 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
35 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
37 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
39 2 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
41 Form 1.Pdf
42 Form 2.Pdf
43 Form 3.Pdf
44 Disclosure Of Sold And Booked Inventory.Pdf
45 Withdrawal Update Form 1.Pdf
49 Withdrawal Update Form 2.Pdf
53 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank KOTAK MAHINDRA BANK LIMITED
IFSC KKBK0001418
Branch Address MIRA ROAD EAST
Country/City