Ishwar Precious Galaxy RERA Details - P51700051722, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Ishwar Precious Galaxy under registration P51700051722 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700051722
  • Project Name PRECIOUS GALAXY WING C
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Ambarnath(M Cl)
  • Original Completion 31 December 2025
  • Revised Completion 31 December 2025
  • Project Area (in Sq.mt.) 450.0
  • Total Buildings/Towers 1
  • Documents 32 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 27 June 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Shree Radhe Builders and Developers

Promoters, Co-promoters & Members

NameRoleAddress
Suresh Dhanraj DhamejaPartnerThane, MAHARASHTRA
Haresh Bhajanlal MattaPartnerThane, MAHARASHTRA
Ankit Sanjay AgarwalPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
PRECIOUS GALAXY WING C PRECIOUS GALAXY WING C 10 1 8 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 17
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 11 units · avg area 49.76 Sq.mt.
3 BHK 5 units · avg area 67.97 Sq.mt.
4 BHK 1 unit · avg area 79.12 Sq.mt.
  • PRECIOUS GALAXY WING C
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 51.7 3 3
2BHK 51.97 1 1
3BHK 67.97 5 0
2BHK 53.79 1 0
4BHK 79.12 1 0
2BHK 47.29 1 0
2BHK 51.83 2 2
2BHK 45.17 3 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • PRECIOUS GALAXY WING C
PRECIOUS GALAXY WING C · Overall Progress 85%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work90%
Sanitary Fittings within the flats / premises
In Progress
% Work90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work85%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 1 B Details Of Encumbrances Concerned To Legal.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval NA Order For Plotted Development.Pdf
7 1 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration About Commencement Certificate.Pdf
9 1 Declaration In FORM B.Pdf
10 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
14 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
15 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
16 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
17 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
18 1 CERSAI Details.Pdf
19 2 CERSAI Details.Pdf
20 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
21 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
22 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
23 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
24 1 Proforma Of Allotment Letter.Pdf
25 1 Proforma Of Agreement For Sale.Pdf
26 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
27 1 Deviation Report With Respect To Allotment Letter.Pdf
28 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
33 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
35 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0006136
Branch Address Shop No1, 2, Uma Galaxy, Near Ganpati Mandir, Titwala East, Kalyan 421605
Country/City