Kalpataru Hills Phase II RERA Details - P51700000584, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kalpataru Hills Phase II under registration P51700000584 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700000584
  • Project Name Kalpataru Hills - Building 2A
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 30 December 2022
  • Revised Completion 30 December 2022
  • Project Area (in Sq.mt.) 534.0
  • Total Buildings/Towers 1
  • Documents 22 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 18 July 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2022 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2022 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Kalpataru Properties (Thane) Pvt. Ltd.
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Kalpataru Hills 1-ABCD and 2-BCKalpataru Hills Opp TikujiNiwadi Off Ghodbunder Road Thane W 400 61017546CompletedResidential / Group Housing25392016-03-312016-04-16NoNA
Siddhachal Phase VIII Bldg No 4off Pokhran Road No2 Majiwade Thane West - 400 610.10637.43CompletedResidential / Group Housing11002013-12-312013-10-15NoNA
Siddhachal Elite Bldg No 1BOff Pokhran Road No2 Majiwade Thane West - 4006108494CompletedResidential / Group Housing1792015-09-302015-12-01NoNA
Kalpataru Hills - Building 2AKalpataru Hills Opp TikujiNiwadi Off Ghodbunder Road Thane W 400 610534CompletedResidential / Group Housing1752021-12-312020-07-12NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Kalpataru Hills - Building 2A Wing 2A - Pristine 0 233 24 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 80
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 7 units · avg area 260.05 Sq.mt.
1RK 7 units · avg area 316.82 Sq.mt.
3 BHK 66 units · avg area 6064.67 Sq.mt.
  • Wing 2A - Pristine
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3 BHK 6064.67 66 61
1BHK 260.05 7 7
1RK 316.82 7 7
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 32.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 80.0% Aggregate Area Of Recreational Open Space 61.0% Open Parking % not reported
Club House, Swimming Pool & Other Recreation Areas 100.0% Common Basement And Podiums 100.0% Na % not reported
Na % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Wing 2A - Pristine
Wing 2A - Pristine · Overall Progress 99%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work96%
Sanitary Fittings within the flats / premises
In Progress
% Work99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work89%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 2 Details Of Encumbrances.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval (IOD).Pdf
7 1 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration In FORM B.Pdf
9 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
10 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
11 1 Certificates Of CA (Form 3).Pdf
12 1 Certificates Of CA (Form 5).Pdf
13 2 Certificates Of CA (Form 5).Pdf
14 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
15 1 Proforma Of Allotment Letter.Pdf
16 2 Proforma Of Allotment Letter.Pdf
17 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
18 1 Certificates Of Architect (Form 4).Pdf
19 1 Status Of Formation Of Legal Entity (Society Co Op Etc.).Pdf
20 1 Other.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000004
Branch Address Free Press House, 215, Nariman Point, Mumbai - 400021