residential Ready to Move Source: rera.mh

Mangeshi Woods RERA Details - P51700034351, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Mangeshi Woods under registration P51700034351 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700034351
  • Project Name Mangeshi Woods
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Chikanghar
  • Original Completion 30 November 2025
  • Revised Completion 30 November 2025
  • Project Area (in Sq.mt.) 2,870.07
  • Total Buildings/Towers 2
  • Documents 56 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 04 April 2022 Expected commencement of civil works and foundation on site.
Original Completion 30 November 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 November 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Mangeshi SaharaChikanghar Kalyan West10060CompletedResidential / Group Housing61932010-12-312010-11-16NoNA
Mangeshi Srushti-IKhadakpada Nr. Vasantvali Gandhare Kalyan West5160CompletedResidential / Group Housing41542010-12-312010-11-16NoNA
Chandrabhaga TowerShree Complex Chowk Kolivali Kalyan West1140CompletedResidential / Group Housing1532010-08-312010-03-30NoNA
Appaji DhamShree Complex Chowk Wadeghar Kalyan West2914CompletedResidential / Group Housing2942012-09-302012-03-22NoNA
Mangeshi Srushti-IIKhadakpada Nr. Vasantvally Kalyan West13544CompletedResidential / Group Housing31792012-03-312012-03-28NoNA
Mangeshi City-IShree Complex Chowk Kolivali Kalyan West11680CompletedResidential / Group Housing73952013-03-312012-10-10NoNA
Mangeshi City-IIShree Complex Chowk Kolivali Kalyan West4770CompletedResidential / Group Housing31302013-06-302013-02-14NoNA
Mangeshi ViharShree Complex Chowk Wadeghar Kalyan West2075CompletedResidential / Group Housing2662013-06-302013-03-19NoNA
VishnukunjAdharwadi Chowk Kalyan West468CompletedResidential / Group Housing1152013-09-302013-05-28NoNA
Chandrabhaga-IIShree Complex Chowk Kolivali Kalyan West960CompletedResidential / Group Housing2632014-06-302014-01-31NoNA
Mangeshi EliteRambag Lane No.4 end Chikanghar Kalyan West8170CompletedResidential / Group Housing51752014-12-312014-10-28NoNA
Mangeshi FlooraRambaug Lane No.4 end Chikanghar Kalyan West6301CompletedResidential / Group Housing21102015-09-302015-06-01NoNA
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address wJXynnNL4BMyGiGBuT/7hw6cxtRzpEXoRZA23zX2XXcqo6PeXbstVY0InWyMe8o4

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Mangeshi Woods A Wing 18 95 23 0 0 NA
Mangeshi Woods B Wing 0 4 3 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 137
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 50 units · avg area 39.85 Sq.mt.
2 BHK 84 units · avg area 54.08 Sq.mt.
Shop 3 units · avg area 14.59 Sq.mt.
  • A Wing
  • B Wing
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 38.7 46 25
2BHK 55.74 23 10
2BHK 52.31 38 9
Shop 16.47 1 0
Shop 13.9 1 0
Shop 13.39 1 0
2BHK 55.34 23 13
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A Wing
  • B Wing
A Wing · Overall Progress 40%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
In Progress
% Work35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
1 1 PAN Card.Pdf
Mh Certificate Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 2 Details Of Encumbrances.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 1 Building Plan Approval NA Order For Plotted Development.Pdf
7 1 Commencement Certificates NA Order For Plotted Development.Pdf
8 2 Commencement Certificates NA Order For Plotted Development.Pdf
9 3 Commencement Certificates NA Order For Plotted Development.Pdf
10 4 Commencement Certificates NA Order For Plotted Development.Pdf
11 1 Declaration About Commencement Certificate.Pdf
12 1 Declaration In FORM B.Pdf
13 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
14 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
15 1 CERSAI Details.Pdf
16 1 Disclosure Of Sold Booked Inventory.Pdf
17 2 Disclosure Of Sold Booked Inventory.Pdf
18 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
19 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
20 1 Proforma Of Allotment Letter.Pdf
22 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
23 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
24 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
25 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
26 5 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
27 6 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
28 7 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
29 8 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
30 9 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
31 10 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
32 11 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
34 7 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
35 11 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
36 10 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
37 9 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
38 8 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
39 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
40 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
41 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
42 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
44 6 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
45 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
46 11 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
47 10 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
48 9 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
49 8 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
50 7 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
51 6 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
52 5 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
53 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
54 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
56 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
57 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
58 Occupational Certificate.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank THE THANE BHARAT SAHAKARI BANK LIMITED
IFSC TBSB0000009
Branch Address Jeevanshree Apt, Shivaji Chowk, Agra Road Kalyan West
Country/City