Marathon Nextown RERA Details - P51700021189, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Marathon Nextown under registration P51700021189 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700021189
  • Project Name MARATHON NEXTOWN RUBY
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 710.0
  • Total Buildings/Towers 1
  • Documents 86 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 14 June 2019 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name MARATHON ENER-GEN

Promoters, Co-promoters & Members

NameRoleAddress
MAYUR RAMNIKLAL SHAHDesignated PartnerMumbai Suburban, MAHARASHTRA
KAIVALYA CHETAN SHAHDesignated PartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
MARATHON NEXTOWN RUBY MARATHON NEXTOWN RUBY 0 0 24 24 24 277 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 275
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 173 units · avg area 27.63 Sq.mt.
2 BHK 88 units · avg area 39.20 Sq.mt.
Shop 14 units · avg area 15.16 Sq.mt.
  • MARATHON NEXTOWN RUBY
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Shop 12.77 1 0
Shop 25.43 1 0
2BHK 39.2 22 20
2BHK 39.39 22 20
2BHK 39.11 44 43
1BHK 29.45 44 43
Shop 8.35 1 0
Shop 13.75 2 0
Shop 24.84 1 0
1BHK 27.87 41 39
Shop 11.84 1 0
Shop 14.02 1 0
Shop 8.55 1 0
Shop 20.05 2 0
Smart 1BHK 23.97 44 42
1BHK 29.26 44 38
Shop 11.28 1 0
Shop 15.18 1 0
Shop 12.32 1 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 50.0%
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • MARATHON NEXTOWN RUBY
MARATHON NEXTOWN RUBY · Overall Progress 66%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work80%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work80%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 Details Of Encumbrances.Pdf
5 1 Copy Of Layout Approval (In Case Of Layout).Pdf
6 2 Copy Of Layout Approval (In Case Of Layout).Pdf
7 3 Copy Of Layout Approval (In Case Of Layout).Pdf
8 4 Copy Of Layout Approval (In Case Of Layout).Pdf
9 1 Building Plan Approval (IOD).Pdf
10 2 Building Plan Approval (IOD).Pdf
11 3 Building Plan Approval (IOD).Pdf
12 4 Building Plan Approval (IOD).Pdf
13 5 Building Plan Approval (IOD).Pdf
14 6 Building Plan Approval (IOD).Pdf
15 7 Building Plan Approval (IOD).Pdf
16 8 Building Plan Approval (IOD).Pdf
17 9 Building Plan Approval (IOD).Pdf
18 10 Building Plan Approval (IOD).Pdf
19 11 Building Plan Approval (IOD).Pdf
20 12 Building Plan Approval (IOD).Pdf
21 13 Building Plan Approval (IOD).Pdf
22 14 Building Plan Approval (IOD).Pdf
23 15 Building Plan Approval (IOD).Pdf
24 16 Building Plan Approval (IOD).Pdf
25 17 Building Plan Approval (IOD).Pdf
26 18 Building Plan Approval (IOD).Pdf
27 1 Commencement Certificates NA Order For Plotted Development.Pdf
28 2 Commencement Certificates NA Order For Plotted Development.Pdf
29 1 Declaration About Commencement Certificate.Pdf
30 1 Declaration In FORM B.Pdf
31 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
32 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
33 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
34 4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
35 5 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
36 6 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
37 7 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
38 8 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
39 9 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
40 10 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
41 11 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
42 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
43 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
44 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
45 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
46 5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
47 6 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
48 7 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
49 8 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
50 9 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
51 10 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
52 11 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
53 12 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
54 13 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
55 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
56 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
57 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
58 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
59 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
60 1 Disclosure Of Sold Booked Inventory.Pdf
61 1 Certificates Of CA (Form 3).Pdf
62 2 Certificates Of CA (Form 3).Pdf
63 3 Certificates Of CA (Form 3).Pdf
64 4 Certificates Of CA (Form 3).Pdf
65 5 Certificates Of CA (Form 3).Pdf
66 6 Certificates Of CA (Form 3).Pdf
67 7 Certificates Of CA (Form 3).Pdf
68 8 Certificates Of CA (Form 3).Pdf
69 9 Certificates Of CA (Form 3).Pdf
70 10 Certificates Of CA (Form 3).Pdf
71 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
72 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
73 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
74 1 Proforma Of Allotment Letter.Pdf
88 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
94 Form 1.Pdf
95 Form 2.Pdf
96 Form 3.Pdf
97 Disclosure Of Sold And Booked Inventory.Pdf
110 Withdrawal Update Form 1.Pdf
112 Withdrawal Update Form 2.Pdf
114 Withdrawal Update Form 3.Pdf
116 Form 2A (FY 2025 2026).Pdf
117 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000652
Branch Address 5 6 7 JALARAM ASHISH CO SOC DEVIDAYAL ROAD MULUND WEST 400080