Siddique Ruby Apartments RERA Details - P51700009674, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Siddique Ruby Apartments under registration P51700009674 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700009674
  • Project Name SIDDIQUEE COMPLEX
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 30 June 2022
  • Revised Completion 30 June 2025
  • Project Area (in Sq.mt.) 4,210.0
  • Total Buildings/Towers 2
  • Documents 34 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 22 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2022 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SIDDIQUEE CONSTRUCTION CO.

Promoters, Co-promoters & Members

NameRoleAddress
IRFAN ALAM SIDDIQUEEPartnerMumbai Suburban, MAHARASHTRA
GULNAR ALAM SIDDIQUEEPartnerMumbai Suburban, MAHARASHTRA
RIZWAN ALAM SIDDIQUEEPartnerMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SIDDIQUEE COMPLEX SIDDIQUEE MAGNUM TOWER 30 12 15 0 0 NA
SIDDIQUEE COMPLEX SIDDIQUEE RUBY TOWER 3 11 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 105
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 33 units · avg area 36.52 Sq.mt.
2 BHK 37 units · avg area 53.12 Sq.mt.
3 BHK 33 units · avg area 69.47 Sq.mt.
4 BHK 2 units · avg area 107.76 Sq.mt.
  • SIDDIQUEE MAGNUM TOWER
  • SIDDIQUEE RUBY TOWER
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3BHK 97.54 1 1
4BHK 107.76 2 0
2BHK 55.74 1 0
1BHK 37.16 11 2
3BHK 60.38 1 1
3BHK 66.88 18 7
3BHK 61.31 5 1
3BHK 65.03 1 0
3BHK 79.89 7 0
2BHK 41.8 1 0
2BHK 47.38 17 4
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SIDDIQUEE MAGNUM TOWER
  • SIDDIQUEE RUBY TOWER
SIDDIQUEE MAGNUM TOWER · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval (IOD).Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 1 Declaration About Commencement Certificate.Pdf
8 1 Declaration In FORM B.Pdf
9 2 Declaration In FORM B.Pdf
10 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
11 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
12 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
13 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
14 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
15 1 Engineers Certificate On Quality Assurance (Form 2A FY 2019 20).Pdf
16 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
17 2 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
18 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
19 1 Disclosure Of Sold Booked Inventory.Pdf
20 2 Disclosure Of Sold Booked Inventory.Pdf
21 3 Disclosure Of Sold Booked Inventory.Pdf
22 4 Disclosure Of Sold Booked Inventory.Pdf
23 1 Certificates Of CA (Form 3).Pdf
24 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
25 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2017 18).Pdf
26 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
27 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
28 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
29 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
30 1 Proforma Of Allotment Letter.Pdf
31 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
IFSC SBIN0031631
Branch Address LOKHANDWALA COMPLEX ANDHERI WEST MUMBAI 400078
Country/City