residential Under Construction Source: rera.mh

Anshul Unity Towers RERA Details - P52100080684, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Anshul Unity Towers under registration P52100080684 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100080684
  • Project Name UNITY TOWERS
  • Project Type Others
  • Project Status Under Construction
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Hadapsar
  • Original Completion 03 March 2028
  • Revised Completion 03 March 2028
  • Project Area (in Sq.mt.) 3,892.0
  • Total Buildings/Towers 2
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 June 2025 Expected commencement of civil works and foundation on site.
Original Completion 03 March 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 03 March 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Anshul Buildcon

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
UNITY TOWERS Wing A 0 117 9 11 9 81 NA
UNITY TOWERS Wing B 0 0 10 12 8 48 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 129
Configurations 5
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 100 units · avg area 62.30 Sq.mt.
Shop 8 units · avg area 37.96 Sq.mt.
Office space 8 units · avg area 67.01 Sq.mt.
Office Landowner 7 units · avg area 65.82 Sq.mt.
Shop Landowner 6 units · avg area 46.89 Sq.mt.
  • Wing A
  • Wing B
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 68.29 1 0
Shop 57.79 1 0
2BHK 68.5 1 0
2BHK 70.44 6 0
2BHK 57.35 16 0
2BHK Landowner 68.29 1 0
2BHK Landowner 70.44 4 0
2BHK Landowner 59.0 3 0
Shop 73.2 1 0
Shop 45.84 1 0
Shop 38.38 1 0
Shop 29.71 1 0
Office space 52.16 1 0
Shop 18.95 1 0
Shop 18.46 1 0
Shop 21.34 1 0
2BHK 57.56 3 0
2BHK 59.0 3 0
2BHK 67.22 2 0
2BHK Landowner 57.35 8 0
2BHK Landowner 57.56 3 0
2BHK Landowner 67.43 1 0
Office space 75.96 2 0
Office space 81.84 2 0
Office space 45.99 2 0
Office Landowner 52.16 2 0
Office space 76.31 1 0
Shop Landowner 71.43 1 0
Shop Landowner 33.84 1 0
Shop Landowner 67.21 1 0
Office Landowner 76.31 2 0
Office Landowner 75.96 1 0
Office Landowner 81.84 1 0
Shop Landowner 18.46 1 0
Shop Landowner 18.95 1 0
Shop Landowner 71.44 1 0
Office Landowner 45.99 1 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 25.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Wing A
  • Wing B
Wing A · Overall Progress 31%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
In Progress
% Work36%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work2%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
46 Withdrawal Update Form 1.Pdf
51 Withdrawal Update Form 2.Pdf
56 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0005196
Branch Address GROUND FLOOR SHOP NO 7 AND 8 AND MEZZANINE OFFICE NO 102, FORTUNE EMPRESS, SR NO 1611245, HANDEWADI MANTARWADI ROAD
Country/City