RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100006997
- Project Name ARCHANA KOHINOOR GLORY-PHASE II
- Project Type Others
- Project Status Ready to Move
- State MAHARASHTRA
- District Pune
- Taluka Haveli
- Village MOHAMMADWADI
- Original Completion 31 December 2022
- Revised Completion 30 December 2023
- Project Area (in Sq.mt.) 8,815.22
- Total Buildings/Towers 2
- Documents 21 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| MANSUKH DEVSHI VELANI | Partner |
| AMBRESHWAR KASHINATH CHIKALE | Authorized Signatory |
| KARAN SHANTILAL JABUANI | Partner |
| RAMNIKLAL DEVSHI VELANI | Partner |
| NITIN KESHVJI PARVADIYA | Partner |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|
| ARCHANA KOHINOOR GLORY-PHASE II | Building B | 2 | 1 | 0 | 11 | 0 | 0 | 30 |
| ARCHANA KOHINOOR GLORY-PHASE II | Building C | 2 | 1 | 0 | 11 | 1 | 0 | 31 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- Building B
- Building C
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2BHK | 46.94 | 4 | 0 |
| 3BHK | 67.73 | 4 | 0 |
| 2BHK | 50.83 | 4 | 0 |
| 2BHK | 53.72 | 4 | 0 |
| 2BHK | 46.38 | 4 | 0 |
| 3BHK | 66.58 | 4 | 0 |
| 2.5BHK | 51.00 | 1 | 0 |
| 3.5BHK | 77.72 | 1 | 0 |
| 2.5BHK | 59.55 | 1 | 0 |
| 2.5BHK | 62.22 | 1 | 0 |
| 2BHK | 51.70 | 4 | 0 |
| 2BHK | 50.49 | 5 | 0 |
| 2BHK | 46.66 | 1 | 0 |
| SHOP | 35.32 | 1 | 0 |
| SHOP | 29.98 | 1 | 0 |
| SHOP | 30.91 | 1 | 0 |
| SHOP | 37.22 | 1 | 0 |
| SHOP | 17.66 | 1 | 0 |
| SHOP | 26.84 | 1 | 0 |
| 3BHK | 66.56 | 1 | 0 |
| 2BHK | 50.22 | 5 | 0 |
| 2BHK | 52.15 | 1 | 0 |
| 2BHK | 53.05 | 4 | 0 |
| 2BHK | 50.68 | 4 | 0 |
| SHOP | 103.74 | 1 | 0 |
| SHOP | 77.01 | 1 | 0 |
| SHOP | 38.18 | 1 | 0 |
| SHOP | 29.05 | 1 | 0 |
| SHOP | 26.91 | 1 | 0 |
| SHOP | 31.02 | 1 | 0 |
| SHOP | 35.65 | 1 | 0 |
| SHOP | 39.69 | 1 | 0 |
| SHOP | 40.93 | 1 | 0 |
| SHOP | 101.19 | 3 | 3 |
| 2.5BHK | 61.11 | 1 | 0 |
| 2.5BHK | 60.04 | 1 | 0 |
| 2BHK | 52.18 | 4 | 0 |
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2BHK | 48.92 | 5 | 0 |
| 3BHK | 72.35 | 1 | 0 |
| 2BHK | 45.77 | 4 | 0 |
| 2BHK | 49.87 | 4 | 0 |
| SHOP | 26.41 | 1 | 0 |
| SHOP | 26.55 | 1 | 0 |
| SHOP | 33.48 | 1 | 0 |
| SHOP | 26.57 | 1 | 0 |
| SHOP | 25.72 | 1 | 0 |
| SHOP | 20.40 | 1 | 0 |
| SHOP | 134.93 | 1 | 0 |
| 2BHK | 51.34 | 1 | 0 |
| 2BHK | 48.77 | 4 | 0 |
| 3BHK | 71.42 | 4 | 0 |
| 2BHK | 49.71 | 4 | 0 |
| 3BHK | 72.68 | 4 | 0 |
| SHOP | 28.07 | 1 | 0 |
| SHOP | 19.39 | 1 | 0 |
| SHOP | 25.57 | 1 | 0 |
| SHOP | 38.18 | 1 | 0 |
| SHOP | 29.06 | 1 | 0 |
| 2BHK | 49.54 | 1 | 0 |
| 2BHK | 49.19 | 1 | 0 |
| 2BHK | 57.18 | 5 | 0 |
| 2BHK | 45.02 | 5 | 0 |
| 2BHK | 46.06 | 1 | 0 |
| 2.5BHK | 56.67 | 1 | 0 |
| 2.5BHK | 55.59 | 1 | 0 |
| 3.5BHK | 79.91 | 1 | 0 |
| 2BHK | 57.04 | 5 | 0 |
| 2BHK | 44.94 | 5 | 0 |
| 2BHK | 44.78 | 4 | 0 |
| 2BHK | 49.90 | 1 | 0 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 61 | 3 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths % not reported | Water Conservation Rainwater Harvesting 100% | Energy Management 50% |
| Fire Protection And Fire Safety Requirements 80% | Electrical Meter Room Substation Receivingstation 80% | Aggregate Area Of Recreational Open Space 100% |
| Open Parking 100% | Water Supply 100% | Sewerage 100% |
| Storm Water Drains % not reported | Landscaping Tree Planting 100% | Street Lighting 100% |
| Community Buildings 100% | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal 100% |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- Building B
- Building C
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | AXIS BANK LTD |
|---|---|
| IFSC | UTIB0000305 |