Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Calyx Vanalika Phase III 3B RERA Details - P52100016963, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Calyx Vanalika Phase III 3B under registration P52100016963 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100016963
  • Project Name VANALIKA-PARADISE- III -3B
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Mulshi
  • Village Pirangut
  • Original Completion 30 December 2023
  • Revised Completion 30 December 2023
  • Project Area (in Sq.mt.) 5,436.13
  • Total Buildings/Towers 1
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 June 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name M/S. AVIOR MAJESTIQUE PROPERTIES

Promoters, Co-promoters & Members

NameRoleAddress
SUNIL SOMANIPartnerPune, MAHARASHTRA
MANISH DWARKADAS MAHESHWARIPartnerPune, MAHARASHTRA
RAHUL PRADIP RATHIPartnerPune, MAHARASHTRA
SAURABH SUNIL MUTHAPartnerPune, MAHARASHTRA
MAJESTIQUE LANDMARK PVT LTD THROUGH DIRECTOR MANISH MAHESWARI NAPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
VANALIKA-PARADISE- III -3B BUILDING -3B 0 15 16 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 166
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 110 units · avg area 26.32 Sq.mt.
2 BHK 56 units · avg area 40.34 Sq.mt.
  • BUILDING -3B
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 40.34 56 53
1BHK 26.32 110 110
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 100.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • BUILDING -3B
BUILDING -3B · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank THE SHAMRAO VITHAL COOPERATIVE BANK
IFSC SVCB0000051
Branch Address SHOP NO 9 TO 14, CHAPHEKAR CENTRE, NEAR HOTEL UTSAV, PUNE SATARA ROAD, PUNE - 411037
Country/City