residential Partially Ready To Move Source: rera.mh

Garve Eastern River Residency RERA Details - P52100033276, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Garve Eastern River Residency under registration P52100033276 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100033276
  • Project Name Eastern River Residency Wing D
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Pimpale Gurav
  • Original Completion 31 December 2025
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 1,800.0
  • Total Buildings/Towers 1
  • Documents 18 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 15 February 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
TreasureKashid Park Pimple Gurav Pune.1392CompletedIndustrial82652012-03-312012-03-31NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Eastern River Residency Wing D Wing D 0 140 26 26 26 140 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 140
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 92 units · avg area 58.75 Sq.mt.
3 BHK 48 units · avg area 80.23 Sq.mt.
  • Wing D
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3BHK 80.23 48 40
2BHK 58.17 44 43
2BHK 59.28 48 46
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 30.0% Water Supply 30.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 30.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 30.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 30.0%
Electrical Meter Room, Sub-station, Receiving Station 30.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Wing D
Wing D · Overall Progress 68%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work87%
Sanitary Fittings within the flats / premises
In Progress
% Work50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work92%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work98.57%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work18.45%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
68 Form 1.Pdf
69 Form 2.Pdf
70 Form 3.Pdf
71 Disclosure Of Sold And Booked Inventory.Pdf
72 Withdrawal Update Form 1.Pdf
75 Withdrawal Update Form 2.Pdf
78 Withdrawal Update Form 3.Pdf
81 Form 2A (FY 2021 2022).Pdf
82 Form 2A (FY 2022 2023).Pdf
83 Form 2A (FY 2023 2024).Pdf
84 Form 2A (FY 2024 2025).Pdf
85 Form 5 (FY 2024 2025).Pdf
86 Form 5 (FY 2021 2022).Pdf
87 Form 5 (FY 2022 2023).Pdf
88 Form 5 (FY 2023 2024).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDFC First Bank Ltd
IFSC IDFB0041374
Branch Address Shop No 22 J Jarvari CHS Pimple Saudagar Pune 411027