residential Partially Ready To Move Source: rera.mh

K Raheja Viva Villa RERA Details - P52100028173, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for K Raheja Viva Villa under registration P52100028173 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100028173
  • Project Name Orion, Viva, Pirangut
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Mulshi
  • Village Pirangut
  • Original Completion 29 August 2024
  • Revised Completion 29 August 2024
  • Project Area (in Sq.mt.) 7,320.78
  • Total Buildings/Towers 26
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 10 February 2021 Expected commencement of civil works and foundation on site.
Original Completion 29 August 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 29 August 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name K Raheja Corp Real Estate Private Limited

Promoters, Co-promoters & Members

NameRoleAddress
Ravi Chandru RahejaDirectorMumbai Suburban, MAHARASHTRA
Neel Chandru RahejaDirectorMumbai Suburban, MAHARASHTRA
Sunil Madhav HingoraniDirectorMumbai Suburban, MAHARASHTRA
Ramesh RanganathanDirectorMumbai City, MAHARASHTRA
Jignasha ThakkarCompany SecretoryMumbai City, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Orion, Viva, Pirangut Twin Villa No F1 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F2 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F3 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F4 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F5 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F6 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F7 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F8 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F9 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F10 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F11 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F12 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F13 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F14 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F15 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F16 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F17 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F18 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F19 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F20 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F21 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F22 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F23 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F24 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F25 1 0 2 0 0 NA
Orion, Viva, Pirangut Twin Villa No F26 1 0 2 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Internal Roads & Footpaths % not reported Internal Roads & Footpaths % not reported
Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0% Storm Water Drains 100.0%
Landscaping & Tree Planting % not reported Landscaping & Tree Planting % not reported Landscaping & Tree Planting 100.0%
Street Lighting 100.0% Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported
Treatment And Disposal Of Sewage And Sullage Water 100.0% Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Electrical Meter Room, Sub-station, Receiving Station % not reported Electrical Meter Room, Sub-station, Receiving Station 90.0%
Aggregate Area Of Recreational Open Space % not reported Open Parking 100.0% Open Parking 92.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Twin Villa No F1
  • Twin Villa No F2
  • Twin Villa No F3
  • Twin Villa No F4
  • Twin Villa No F5
  • Twin Villa No F6
  • Twin Villa No F7
  • Twin Villa No F8
  • Twin Villa No F9
  • Twin Villa No F10
  • Twin Villa No F11
  • Twin Villa No F12
  • Twin Villa No F13
  • Twin Villa No F14
  • Twin Villa No F15
  • Twin Villa No F16
  • Twin Villa No F17
  • Twin Villa No F18
  • Twin Villa No F19
  • Twin Villa No F20
  • Twin Villa No F21
  • Twin Villa No F22
  • Twin Villa No F23
  • Twin Villa No F24
  • Twin Villa No F25
  • Twin Villa No F26
Twin Villa No F1 · Overall Progress 0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
138 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.