residential Partially Ready To Move Source: rera.mh

Kohinoor Courtyard One RERA Details - P52100032001, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kohinoor Courtyard One under registration P52100032001 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100032001
  • Project Name COURTYARD ONE C BLDG
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Pune City
  • Original Completion 31 December 2026
  • Revised Completion 31 December 2026
  • Project Area (in Sq.mt.) 11,119.3
  • Total Buildings/Towers 1
  • Documents 14 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 03 December 2021 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name COURTYARD ONE VENTURES LLP

Promoters, Co-promoters & Members

NameRoleAddress
VINEET GOYALPartnerPune, MAHARASHTRA
RAJESH GOYALPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
COURTYARD ONE C BLDG C 7 359 26 24 22 257 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 257
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 169 units · avg area 59.93 Sq.mt.
3 BHK 88 units · avg area 78.30 Sq.mt.
  • C
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 59.93 169 156
3BHK 78.3 88 86
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 90.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 90.0% Landscaping & Tree Planting 90.0% Street Lighting 90.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 80.0% Solid Waste Management And Disposal 80.0%
Water Conservation /Rain Water Harvesting 50.0% Energy Managemcnt 50.0% Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station 90.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • C
C · Overall Progress 98%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
68 Form 1.Pdf
69 Form 2.Pdf
70 Form 3.Pdf
71 Disclosure Of Sold And Booked Inventory.Pdf
142 Form 2A (FY 2024 2025).Pdf
143 Form 2A (FY 2021 2022).Pdf
144 Form 2A (FY 2022 2023).Pdf
145 Form 2A (FY 2023 2024).Pdf
146 Form 5 (FY 2024 2025).Pdf
147 Form 5 (FY 2021 2022).Pdf
148 Form 5 (FY 2022 2023).Pdf
149 Form 5 (FY 2023 2024).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0000600
Branch Address 1ST FLR, PLOT NO 421/A NR SYMBIOSIS ATUR CENTRE, ASHOKNAGAR PUNE 411016
Country/City