Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Partially Ready To Move Source: rera.mh

Kumar Prospera Hadapsar RERA Details - P52100035207, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kumar Prospera Hadapsar under registration P52100035207 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100035207
  • Project Name Kumar Prospera - A7 and A8
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Hadapsar
  • Original Completion 01 July 2026
  • Revised Completion 01 July 2027
  • Project Area (in Sq.mt.) 12,028.27
  • Total Buildings/Towers 2
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 10 May 2022 Expected commencement of civil works and foundation on site.
Original Completion 01 July 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 01 July 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name Kumar Agro Products Pvt Ltd - Kumar Company (Now known as Kumar Construction and Properties Pvt Ltd) JV

Promoters, Co-promoters & Members

NameRoleAddress
Manish Vimalkumar JainDirectorPune, MAHARASHTRA
Rajiv Shyamlal KhianiDirectorPune, MAHARASHTRA
Bhavinkumar Nagraj JainDirectorMumbai Suburban, MAHARASHTRA
M/s Kumar Company CompanyMemberPune, MAHARASHTRA
Smt Pushpa Vimalkumar Jain JainMemberPune, MAHARASHTRA
Manish Vimalkumar Jain JainDirectorPune, MAHARASHTRA
Mr. Rajas Vimalkumar Jain JainMemberPune, MAHARASHTRA
Mr. Ameya Inderkumar Jain JainMemberPune, MAHARASHTRA
Ms. Apurva Inderkumar Jain JainMemberPune, MAHARASHTRA
Mrs. Rashmi Ritesh Chandalia ( Jain) JainMemberMumbai City, MAHARASHTRA
Smt. Ranjana Inderkumar Jain JainMemberPune, MAHARASHTRA
Mr. Kewalkumar Kesarimal Jain JainDirectorPune, MAHARASHTRA
M/S Kumar Agro Products Pvt. Ltd. Kumar Agro Products Pvt LtdMemberPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Kumar Prospera - A7 and A8 A7 0 167 25 25 23 92 NA
Kumar Prospera - A7 and A8 A8 0 142 22 22 20 77 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 169
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 88 units · avg area 76.05 Sq.mt.
3 BHK 81 units · avg area 109.00 Sq.mt.
  • A7
  • A8
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 87.5 4 4
3BHK 109.0 42 42
2BHK 75.5 46 46
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 25.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings 80.0% Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A7
  • A8
A7 · Overall Progress 70%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work87%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work3%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
107 Form 2A (FY 2025 2026).Pdf
108 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank KOTAK MAHINDRA BANK LIMITED
IFSC KKBK0000721
Branch Address M-4 , VIRWANI PLAZA 11 EAST STREET, PUNE 411001
Country/City