Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Majestique Aqua RERA Details - P52100020371, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Majestique Aqua under registration P52100020371 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100020371
  • Project Name Aqua Phase III
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Fursungi
  • Original Completion 30 December 2023
  • Revised Completion 30 December 2023
  • Project Area (in Sq.mt.) 3,260.0
  • Total Buildings/Towers 1
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 April 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name M/S Majestique Heights

Promoters, Co-promoters & Members

NameRoleAddress
JAVED RIYAZ SHAIKHPartnerPune, MAHARASHTRA
NAVED RIYAZ SHAIKHPartnerPune, MAHARASHTRA
SURESH PREMRAJ KATARIYAPartnerPune, MAHARASHTRA
AMIT ANIL LALWANIPartnerPune, MAHARASHTRA
KUSHALRAJ PREMRAJ KATARIYAPartnerPune, MAHARASHTRA
BHAIRAVSINGH N RAJPUROHITPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Aqua Phase III B-BUILDING 0 44 14 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 127
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 51 units · avg area 31.06 Sq.mt.
2 BHK 76 units · avg area 49.07 Sq.mt.
  • B-BUILDING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1 BHK 27.78 4 4
1 BHK 34.89 10 10
1 BHK 27.32 2 2
2 BHK 54.37 10 10
1 BHK 29.05 8 8
1 BHK 35.22 11 11
2 BHK 42.32 2 2
2 BHK 47.59 4 4
2 BHK 47.59 4 4
2 BHK 47.97 12 12
2 BHK 49.84 4 4
2 BHK 47.89 8 8
2 BHK 50.0 6 6
1 BHK 27.78 4 4
2 BHK 41.86 2 2
2 BHK 42.62 4 4
2 BHK 54.75 12 12
1 BHK 28.35 8 8
2 BHK 47.28 2 2
1 BHK 27.94 4 4
2 BHK 42.79 6 6
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Landscaping & Tree Planting 100.0% Internal Roads & Footpaths 100.0% Water Supply 100.0%
Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0% Storm Water Drains 100.0% Street Lighting 100.0%
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • B-BUILDING
B-BUILDING · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0001032
Branch Address Viman Nagar Pune
Country/City