RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100006995
- Project Name Solitaire Business Hub Viman Nagar Phase 1
- Project Type Commercial
- Project Status Partially Ready To Move
- State Maharashtra
- District Pune
- Taluka Haveli
- Village LOHGAON
- Original Completion 30 June 2022
- Revised Completion 31 March 2025
- Project Area (in Sq.mt.) 37,708.35
- Total Buildings/Towers 1
- Documents 3 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths 99.0% | Internal Roads & Footpaths % not reported | Internal Roads & Footpaths 99.0% |
| Internal Roads & Footpaths 99.0% | Internal Roads & Footpaths % not reported | Water Supply 98.0% |
| Water Supply 98.0% | Water Supply 98.0% | Sewerage (Chamber, Lines, Septic Tank , Stp) 99.0% |
| Sewerage (Chamber, Lines, Septic Tank , Stp) 99.0% | Sewerage (Chamber, Lines, Septic Tank , Stp) 99.0% | Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported |
| Storm Water Drains 95.0% | Storm Water Drains 95.0% | Storm Water Drains 95.0% |
| Storm Water Drains % not reported | Landscaping & Tree Planting 100.0% | Landscaping & Tree Planting % not reported |
| Landscaping & Tree Planting 100.0% | Landscaping & Tree Planting 100.0% | Street Lighting 95.0% |
| Street Lighting % not reported | Street Lighting 95.0% | Street Lighting 95.0% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage And Sullage Water % not reported | Treatment And Disposal Of Sewage And Sullage Water 98.0% |
| Treatment And Disposal Of Sewage And Sullage Water 98.0% | Treatment And Disposal Of Sewage And Sullage Water 98.0% | Solid Waste Management And Disposal 96.0% |
| Solid Waste Management And Disposal % not reported | Solid Waste Management And Disposal 96.0% | Solid Waste Management And Disposal 96.0% |
| Water Conservation /Rain Water Harvesting % not reported | Water Conservation /Rain Water Harvesting 93.0% | Water Conservation /Rain Water Harvesting 93.0% |
| Water Conservation /Rain Water Harvesting 93.0% | Energy Managemcnt % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Fire Protection And Fire Safety Requirements 50.0% | Fire Protection And Fire Safety Requirements 95.0% | Fire Protection And Fire Safety Requirements 95.0% |
| Electrical Meter Room, Sub-station, Receiving Station 90.0% | Electrical Meter Room, Sub-station, Receiving Station 90.0% | Electrical Meter Room, Sub-station, Receiving Station 90.0% |
| Electrical Meter Room, Sub-station, Receiving Station % not reported | Aggregate Area Of Recreational Open Space % not reported | Open Parking % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | HDFC BANK |
|---|---|
| IFSC | HDFC0000007 |
| Branch Address | Bhandarkar Road Pune |