Oxford Manor Crystal RERA Details - P52100020056, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Oxford Manor Crystal under registration P52100020056 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100020056
  • Project Name Manor Crystal
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Mulshi
  • Village Wakad
  • Original Completion 30 December 2022
  • Revised Completion 30 September 2026
  • Project Area (in Sq.mt.) 1,325.0
  • Total Buildings/Towers 2
  • Documents 16 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 25 March 2019 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2022 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 September 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name OXFORD INFRA GROUP

Promoters, Co-promoters & Members

NameRoleAddress
AMAR CHANDRAKANT BHUMKARPartnerPune, MAHARASHTRA
Chandrakant Baburao BhumkarPartnerPune, MAHARASHTRA
Dnyaneshwar baburao BhumkarPartnerPune, MAHARASHTRA
Arun Baburao BhumkarPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Manor Crystal A 0 0 6 6 4 16 NA
Manor Crystal B 0 0 5 5 4 16 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A
  • B
A · Overall Progress 56%
Excavation
Complete
% Work100%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work65%
Sanitary Fittings within the flats / premises
In Progress
% Work10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
243 Form 2A (FY 2018 2019).Pdf
244 Form 2A (FY 2019 2020).Pdf
245 Form 2A (FY 2020 2021).Pdf
246 Form 2A (FY 2021 2022).Pdf
247 Form 2A (FY 2022 2023).Pdf
248 Form 2A (FY 2023 2024).Pdf
250 Form 2A (FY 2024 2025).Pdf
252 Form 5 (FY 2018 2019).Pdf
253 Form 5 (FY 2019 2020).Pdf
254 Form 5 (FY 2020 2021).Pdf
255 Form 5 (FY 2021 2022).Pdf
256 Form 5 (FY 2022 2023).Pdf
257 Form 5 (FY 2023 2024).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank KOTAK MAHINDRA BANK LIMITED
IFSC KKBK0001783
Branch Address WAKAD PUNE
Country/City