RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100050520
- Project Name Vaarivana Phase B-1
- Project Type Residential / Group Housing
- Project Status Partially Ready To Move
- State Maharashtra
- District Pune
- Taluka Mawal
- Village Urse
- Original Completion 01 March 2027
- Revised Completion 01 March 2027
- Project Area (in Sq.mt.) 50,380.36
- Total Buildings/Towers 73
- Documents 3 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role | Address |
|---|---|---|
| Anil Jayram Pharande | Partner | Pune, MAHARASHTRA |
| Pharande Township Private Limited | Partner | Pune, MAHARASHTRA |
| Nitin Govind Sable | Partner | Pune, MAHARASHTRA |
| Surekha Rajeev Sable | Partner | Pune, MAHARASHTRA |
| Ramesh Jayram Pharande | Partner | Pune, MAHARASHTRA |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | No. of Open Parking | No. of Closed Parking | No. of Floors | CC Issued | No. of Habitable Floor | No. of Sanctioned Apartment | Wing Name |
|---|---|---|---|---|---|---|---|---|
| Vaarivana Phase B-1 | Bungalow No B1 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B2 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B3 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B4 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B5 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B6 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B7 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B8 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B9 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B10 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B11 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B12 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B13 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B14 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B15 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B16 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B17 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B18 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B19 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B20 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B21 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B22 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B23 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B24 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B25 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B26 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B94 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B95 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B96 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B97 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B98 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B99 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B100 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B101 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B102 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B103 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B104 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B105 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B106 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B107 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B108 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B109 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B110 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B111 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B112 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B113 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B114 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B115 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B116 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B117 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B118 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B119 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B120 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B121 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B122 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B123 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B124 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B125 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B126 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B127 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B128 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B129 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B130 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B131 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B132 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B133 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B134 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B135 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B136 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B137 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B138 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B139 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
| Vaarivana Phase B-1 | Bungalow No B140 | 0 | 0 | 2 | 2 | 2 | 1 | NA |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths 62.0% | Water Supply 24.0% | Sewerage (Chamber, Lines, Septic Tank , Stp) 22.0% |
| Storm Water Drains 35.0% | Landscaping & Tree Planting 20.0% | Street Lighting 20.0% |
| Community Buildings 20.0% | Treatment And Disposal Of Sewage And Sullage Water % not reported | Solid Waste Management And Disposal % not reported |
| Water Conservation /Rain Water Harvesting % not reported | Energy Managemcnt % not reported | Fire Protection And Fire Safety Requirements % not reported |
| Electrical Meter Room, Sub-station, Receiving Station % not reported | Aggregate Area Of Recreational Open Space 15.0% | Open Parking % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- Bungalow No B1
- Bungalow No B2
- Bungalow No B3
- Bungalow No B4
- Bungalow No B5
- Bungalow No B6
- Bungalow No B7
- Bungalow No B8
- Bungalow No B9
- Bungalow No B10
- Bungalow No B11
- Bungalow No B12
- Bungalow No B13
- Bungalow No B14
- Bungalow No B15
- Bungalow No B16
- Bungalow No B17
- Bungalow No B18
- Bungalow No B19
- Bungalow No B20
- Bungalow No B21
- Bungalow No B22
- Bungalow No B23
- Bungalow No B24
- Bungalow No B25
- Bungalow No B26
- Bungalow No B94
- Bungalow No B95
- Bungalow No B96
- Bungalow No B97
- Bungalow No B98
- Bungalow No B99
- Bungalow No B100
- Bungalow No B101
- Bungalow No B102
- Bungalow No B103
- Bungalow No B104
- Bungalow No B105
- Bungalow No B106
- Bungalow No B107
- Bungalow No B108
- Bungalow No B109
- Bungalow No B110
- Bungalow No B111
- Bungalow No B112
- Bungalow No B113
- Bungalow No B114
- Bungalow No B115
- Bungalow No B116
- Bungalow No B117
- Bungalow No B118
- Bungalow No B119
- Bungalow No B120
- Bungalow No B121
- Bungalow No B122
- Bungalow No B123
- Bungalow No B124
- Bungalow No B125
- Bungalow No B126
- Bungalow No B127
- Bungalow No B128
- Bungalow No B129
- Bungalow No B130
- Bungalow No B131
- Bungalow No B132
- Bungalow No B133
- Bungalow No B134
- Bungalow No B135
- Bungalow No B136
- Bungalow No B137
- Bungalow No B138
- Bungalow No B139
- Bungalow No B140
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | HDFC BANK |
|---|---|
| IFSC | HDFC0000185 |
| Branch Address | Nigdi, Pune |