Pinnacle Neelanchal RERA Details - P52100004125, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Pinnacle Neelanchal under registration P52100004125 in Pune, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100004125
  • Project Name Neelanchal Phase I
  • Project Type Mixed (Plots & Buildings)
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Pune
  • Taluka Mulshi
  • Village Sus
  • Original Completion 31 December 2018
  • Revised Completion 30 December 2026
  • Project Area (in Sq.mt.) 2,190.09
  • Total Buildings/Towers 3
  • Documents 41 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 08 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Pinnacle Vastunirman Pvt. Ltd
Website pinnaclegroup.in
Other Description NA

Promoters, Co-promoters & Members

NameRole
Gajendra Dattatraya PawarAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
Neelanchal Phase I Wing B 2025-12-31 0 1 0 12 1 16 24
Neelanchal Phase I Commercial - 0 1 0 2 1 24 1
Neelanchal Phase I WING A 2025-12-31 0 1 0 12 1 16 1

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 293
Configurations 9
Inventory Type RESIDENTIAL
Configuration Distribution
Option 1 30 units · avg area 14.69 Sq.mt.
2 BHK 188 units · avg area 52.33 Sq.mt.
Option 2 2 units · avg area 15.87 Sq.mt.
Option 3 1 unit · avg area 17.02 Sq.mt.
Option 4 2 units · avg area 20.21 Sq.mt.
Option 5 60 units · avg area 14.51 Sq.mt.
Option 6 2 units · avg area 16.86 Sq.mt.
Option 7 4 units · avg area 15.69 Sq.mt.
Option 8 4 units · avg area 20.03 Sq.mt.
  • Wing B
  • Commercial
  • WING A
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2 BHK Large 52.80 48 48
2 BHK Comfort 51.83 46 46
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 79 0 10
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 100% Water Conservation Rainwater Harvesting 80% Energy Management % not reported
Fire Protection And Fire Safety Requirements 50% Electrical Meter Room Substation Receivingstation 50% Aggregate Area Of Recreational Open Space 25%
Open Parking 5% Water Supply 100% Sewerage 100%
Storm Water Drains 50% Landscaping Tree Planting 100% Street Lighting 100%
Community Buildings 25% Treatment And Disposal Of Sewage Sullage Water 20% Solid Waste Management Disposal 20%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Wing B
  • Commercial
  • WING A
Wing B · Overall Progress 81%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Complete
% Work100%
X number of Slabs of Super Structure
In Progress
% Work13%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work95%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
2 Copy Of The Legal Title Report
3 Copy Of The Legal Title Report
4 Copy Of The Legal Title Report
5 Copy Of The Legal Title Report
1 Details Of Encumbrances
2 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
5 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
6 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
6 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate On Quality Assurance (Form 2A FY 2021-22)
3 Engineers Certificate On Quality Assurance (Form 2A FY 2021-22)
4 Engineers Certificate On Quality Assurance (Form 2A FY 2021-22)
5 Engineers Certificate On Quality Assurance (Form 2A FY 2021-22)
1 Disclosure Of Sold/ Booked Inventory
2 Disclosure Of Sold/ Booked Inventory
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019-20)
1 Proforma Of Allotment Letter
2 Proforma Of Allotment Letter
1 Other
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC Bank Ltd
IFSC HDFC0000007