Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Partially Ready To Move Source: rera.mh

Raviraj One Residency RERA Details - P52100047267, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Raviraj One Residency under registration P52100047267 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100047267
  • Project Name ONE RESIDENCY PHASE 1
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village AMBEGAON KH
  • Original Completion 31 May 2025
  • Revised Completion 30 June 2026
  • Project Area (in Sq.mt.) 2,670.0
  • Total Buildings/Towers 1
  • Documents 9 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 17 October 2022 Expected commencement of civil works and foundation on site.
Original Completion 31 May 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name RAVIRAJ REALTY DEVELOPERS LLP

Promoters, Co-promoters & Members

NameRoleAddress
ABHINANDAN RAVINDRA SAKLAPartnerPune, MAHARASHTRA
RAVINDRA NAUPATLAL SAKLAPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
ONE RESIDENCY PHASE 1 A BUILDING 0 60 17 14 14 138 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 138
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 55 units · avg area 35.71 Sq.mt.
2 BHK 78 units · avg area 43.75 Sq.mt.
5 BHK 5 units · avg area 42.19 Sq.mt.
  • A BUILDING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1.5 BHK 43.23 3 3
1BHK 36.19 50 21
2BHK 42.3 26 20
2BHK 44.48 52 43
1BHK 26.82 2 1
1.5 BHK 40.63 2 2
1BHK 33.7 3 1
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 75.0% Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 75.0%
Storm Water Drains 75.0% Landscaping & Tree Planting 25.0% Street Lighting 50.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 80.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 50.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 75.0%
Electrical Meter Room, Sub-station, Receiving Station 90.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A BUILDING
A BUILDING · Overall Progress 78%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work50%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
149 Form 2A (FY 2022 2023).Pdf
150 Form 2A (FY 2023 2024).Pdf
151 Form 2A (FY 2024 2025).Pdf
152 Form 5 (FY 2022 2023).Pdf
153 Form 5 (FY 2023 2024).Pdf
154 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank INDIAN BANK
IFSC IDIB000N012
Branch Address 613 - B, Parsi Agiyary Compound, New Nana Peth, Pune, 411002
Country/City