Talreja Business Hub RERA Details - P52100078593, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Talreja Business Hub under registration P52100078593 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100078593
  • Project Name TALREJA BUSINESS HUB
  • Project Type Commercial
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Mulshi
  • Village Thergaon
  • Original Completion 01 December 2024
  • Revised Completion 31 December 2025
  • Project Area (in Sq.mt.) 635.66
  • Total Buildings/Towers 1
  • Documents 16 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 27 December 2024 Expected commencement of civil works and foundation on site.
Original Completion 01 December 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Individual

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
TALREJA BUSINESS HUB A BUILDING 14 51 8 8 7 17 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting 100.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A BUILDING
A BUILDING · Overall Progress 91%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
32 2 Copy Of Layout Approval (In Case Of Layout).Pdf
35 2 Declaration In FORM B.Pdf
37 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
39 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
41 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
43 2 Commencement Certificates NA Order For Plotted Development.Pdf
45 2 Building Plan Approval NA Order For Plotted Development.Pdf
48 1 Disclosure Of Sold Booked Inventory.Pdf
50 2 Declaration About Commencement Certificate.Pdf
57 2 Other – Technical.Pdf
61 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
64 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2024 25).Pdf
78 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0005529
Branch Address GR FLR GLOBAL PORT 45 1 TO 45 4 MUMBAI BANGLORE HIGHWAY NR AUDI SHOWROOM BANER PUNE MAHARASHTRA 411045