Tiruupatee Nisarg Homes RERA Details - P52100006956, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Tiruupatee Nisarg Homes under registration P52100006956 in Pune, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100006956
  • Project Name BALAJI NISARG
  • Project Type Residential
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Pune
  • Taluka Haveli
  • Village Shiraswadi
  • Original Completion 30 December 2020
  • Revised Completion 30 June 2021
  • Project Area (in Sq.mt.) 24,610.03
  • Total Buildings/Towers 6
  • Documents 32 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 16 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2020 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2021 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name TIRUUPATEE VASTU NIRMAN PVT LTD
Other Description NA

Promoters, Co-promoters & Members

NameRole
AJEENCKYA FATTESINGH JAGTAPManaging Director
AJEENCKYA FATTESING JAGTAPAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
BALAJI NISARG A TYPE BUILDING BUILDING NO 19 20 21 0 1 0 5 0 15 0
BALAJI NISARG A TYPE BUILDING BUILDING NO 16 17 18 0 1 0 5 0 13 0
BALAJI NISARG A TYPE BUILDING BUILDING NO 10 11 12 13 0 1 0 5 0 16 0
BALAJI NISARG A TYPE BUILDING BUILDING NO 6 7 8 9 0 1 0 5 0 22 0
BALAJI NISARG A TYPE BUILDING BUILDING NO 1 2 3 4 5 0 1 0 5 0 27 0
BALAJI NISARG B TYPE BUILDING BUILDING NO 14 15 0 1 0 5 0 0 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 416
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 152 units · avg area 29.23 Sq.mt.
1 RK 112 units · avg area 18.65 Sq.mt.
2 BHK 152 units · avg area 37.97 Sq.mt.
  • A TYPE BUILDING BUILDING NO 19 20 21
  • A TYPE BUILDING BUILDING NO 16 17 18
  • A TYPE BUILDING BUILDING NO 10 11 12 13
  • A TYPE BUILDING BUILDING NO 6 7 8 9
  • A TYPE BUILDING BUILDING NO 1 2 3 4 5
  • B TYPE BUILDING BUILDING NO 14 15
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1 BHK 29.23 24 24
2 BHK 37.97 24 24
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage 0 0 0
Covered Parking 190 153 90
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 100% Water Conservation Rainwater Harvesting 70% Energy Management 80%
Fire Protection And Fire Safety Requirements % not reported Electrical Meter Room Substation Receivingstation 80% Aggregate Area Of Recreational Open Space % not reported
Open Parking 80% Water Supply 100% Sewerage 100%
Storm Water Drains % not reported Landscaping Tree Planting 85% Street Lighting 70%
Community Buildings % not reported Treatment And Disposal Of Sewage Sullage Water 80% Solid Waste Management Disposal % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A TYPE BUILDING BUILDING NO 19 20 21
  • A TYPE BUILDING BUILDING NO 16 17 18
  • A TYPE BUILDING BUILDING NO 10 11 12 13
  • A TYPE BUILDING BUILDING NO 6 7 8 9
  • A TYPE BUILDING BUILDING NO 1 2 3 4 5
  • B TYPE BUILDING BUILDING NO 14 15
A TYPE BUILDING BUILDING NO 19 20 21 · Overall Progress 79%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration About Commencement Certificate
1 Declaration In FORM B
1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
5 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
6 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project)
1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
6 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project)
1 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
4 Engineers Certificate On Quality Assurance (Form 2A FY 2020-21)
1 Disclosure Of Sold/ Booked Inventory
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019-20)
1 Proforma Of Allotment Letter
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Saraswat Co-operative Bank Ltd
IFSC SRCB0000375
Country/City