Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.mh

Tulip Infinity World Phase 2 RERA Details - P52100031397, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Tulip Infinity World Phase 2 under registration P52100031397 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100031397
  • Project Name INFINITY WORLD
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Pune
  • Taluka Mulshi
  • Village Punawale
  • Original Completion 30 June 2026
  • Revised Completion 30 June 2026
  • Project Area (in Sq.mt.) 757.0
  • Total Buildings/Towers 1
  • Documents 2 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 23 October 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 June 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name TULIP DEVELOPERS
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address ptkr8TkCm6NIUijMk0k8Fj3EU1raHjAZ1cRADxRZZ8j/tDhM/oUp1sRvE2O3XTjC

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
INFINITY WORLD MHADA BUILDING AND CLUB HOUSE 0 14 7 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 27
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 27 units · avg area 37.63 Sq.mt.
  • MHADA BUILDING AND CLUB HOUSE
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 36.96 3 3
2BHK 36.09 3 3
2BHK 38.06 3 3
2BHK 37.73 3 3
2BHK 36.65 3 3
2BHK 36.1 3 2
2BHK 40.22 3 1
2BHK 38.41 6 6
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 50.0% Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 70.0%
Storm Water Drains 75.0% Landscaping & Tree Planting 20.0% Street Lighting 10.0%
Community Buildings 80.0% Treatment And Disposal Of Sewage And Sullage Water 90.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 50.0% Energy Managemcnt 20.0% Fire Protection And Fire Safety Requirements 20.0%
Electrical Meter Room, Sub-station, Receiving Station 80.0% Aggregate Area Of Recreational Open Space 20.0% Open Parking 20.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • MHADA BUILDING AND CLUB HOUSE
MHADA BUILDING AND CLUB HOUSE · Overall Progress 70%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work85%
Sanitary Fittings within the flats / premises
In Progress
% Work10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work10%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank AXIS BANK
IFSC UTIB0003144
Branch Address D Y Patil College Road Ravet Pune 412101
Country/City