Rohan Abhilasha 3 RERA Details - P52100050453, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Rohan Abhilasha 3 under registration P52100050453 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100050453
  • Project Name Rohan Abhilasha 3
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village WAGHOLI
  • Original Completion 31 March 2027
  • Revised Completion 31 March 2027
  • Project Area (in Sq.mt.) 12,600.0
  • Total Buildings/Towers 3
  • Documents 4 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 17 April 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 March 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 March 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Rohan Housing Pvt Ltd
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Rohan PrathamaS NO 137 HINJEWADI 41105713450CompletedResidential / Group Housing22962024-12-312022-12-28NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Rohan Abhilasha 3 Wing-A 0 105 13 13 11 118 NA
Rohan Abhilasha 3 Wing-B 0 140 13 13 11 107 NA
Rohan Abhilasha 3 wing-C 0 72 12 12 11 54 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 90.0% Water Supply 50.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 50.0% Street Lighting 50.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station 20.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Wing-A
  • Wing-B
  • wing-C
Wing-A · Overall Progress 88%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
96 Form 2A (FY 2024 2025).Pdf
97 Form 5 (FY 2024 2025).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000039
Branch Address ICICI BANK LTD, 1194/8, RAMCHANDRA SABHAMANDAP, GHOLE ROAD, SHIVAJINAGAR, PUNE, MAHARASHTRA - 411005
Country/City