Nexus Hyde Park Residency RERA Details - P51700027694, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Nexus Hyde Park Residency under registration P51700027694 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700027694
  • Project Name HYDE PARK RESIDENCY F5 BUILDING PHASE
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Thane (M Corp.)
  • Original Completion 30 September 2023
  • Revised Completion 30 September 2023
  • Project Area (in Sq.mt.) 592.06
  • Total Buildings/Towers 1
  • Documents 25 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 31 December 2020 Expected commencement of civil works and foundation on site.
Original Completion 30 September 2023 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 September 2023 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name NEXUS BUILDERS AND DEVELOPERS PVT LTD
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
HYDE PARK BUILDING NO F2Hyde Park F2 Building Behind Greenwood Complex Off Ghod Bunder Road Thane West2500CompletedIndustrial1562016-12-312017-04-29NoNA
HYDE PARK RESIDENCY R1 R2 R3 R4Hyde Park Residency Behind Greenwood Complex Off Ghod Bunder Road Thane West1551.69CompletedIndustrial142016-12-312017-04-29NoNA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
HYDE PARK RESIDENCY F5 BUILDING PHASE HYDE PARK RESIDENCY F5 BUILDING PHASE 0 1 9 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 14
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 14 units · avg area 38.73 Sq.mt.
  • HYDE PARK RESIDENCY F5 BUILDING PHASE
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 38.4 7 0
1BHK 39.05 7 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 70.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 90.0% Street Lighting 90.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station 80.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • HYDE PARK RESIDENCY F5 BUILDING PHASE
HYDE PARK RESIDENCY F5 BUILDING PHASE · Overall Progress 87%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
In Progress
% Work65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work90%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval NA Order For Plotted Development.Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 1 Declaration About Commencement Certificate.Pdf
8 1 Declaration In FORM B.Pdf
9 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
10 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
11 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
12 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
13 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
14 2 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
15 1 Disclosure Of Sold Booked Inventory.Pdf
16 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
17 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
18 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
19 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
20 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
21 1 Proforma Of Allotment Letter.Pdf
22 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
23 1 Architect’S Certificate On Completion Of Project (Form 4).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0003872
Branch Address Gr Floor Shop 2 and 3 Mint Chambers Manpada Near Hiranandani Meadows Thane West 400 607