Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.mh

Patel Eirene RERA Details - P51700054106, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Patel Eirene under registration P51700054106 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700054106
  • Project Name PATELS EIRENE
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Ambarnath(M Cl)
  • Original Completion 31 August 2026
  • Revised Completion 31 August 2026
  • Project Area (in Sq.mt.) 999.0
  • Total Buildings/Towers 1
  • Documents 37 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 27 December 2023 Expected commencement of civil works and foundation on site.
Original Completion 31 August 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 August 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name PRAMUKH DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
NIKHIL A WALEKARPartnerThane, MAHARASHTRA
RAHUL C WAGHELAPartnerThane, MAHARASHTRA
PATEL RPL REALTY PRIVATE LIMITED THROUGH ITS DIRECTOR ANKIT B PATELPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
PATELS EIRENE PATELS EIRENE 1 1 7 7 7 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 60
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 1 unit · avg area 22.02 Sq.mt.
1 BHK 29 units · avg area 31.20 Sq.mt.
2 BHK 29 units · avg area 38.22 Sq.mt.
3 BHK 1 unit · avg area 53.88 Sq.mt.
  • PATELS EIRENE
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 37.75 1 0
2BHK 40.05 1 0
2BHK 35.02 6 2
2BHK 35.86 5 1
3BHK 53.88 1 1
1RK 22.02 1 1
1BHK 28.71 1 1
1BHK 30.01 5 2
1BHK 30.1 6 6
1BHK 30.57 5 2
1BHK 32.7 11 7
1BHK 32.98 1 1
2BHK 37.16 1 1
2BHK 37.9 6 1
2BHK 40.13 4 2
2BHK 43.2 5 3
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • PATELS EIRENE
PATELS EIRENE · Overall Progress 47%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work15%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 B Details Of Encumbrances Concerned To Legal.Pdf
6 2 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval NA Order For Plotted Development.Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 1 Declaration About Commencement Certificate.Pdf
11 1 Declaration In FORM B.Pdf
12 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
14 1 CERSAI Details.Pdf
15 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
16 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
17 1 Proforma Of Allotment Letter.Pdf
18 1 Proforma Of Agreement For Sale.Pdf
19 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
20 1 Deviation Report With Respect To Allotment Letter.Pdf
21 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
22 1 Other – Legal.Pdf
24 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
25 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
26 4 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
28 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
29 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
30 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
32 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
33 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
34 4 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
35 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
36 Form 1.Pdf
37 Form 2.Pdf
38 Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0000457
Branch Address PANVELKAR, PLAZA STATION ROAD, AMBERNATH EAST 421501
Country/City