Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Regency Sarvam RERA Details - P51700029930, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Regency Sarvam under registration P51700029930 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700029930
  • Project Name Regency Sarvam Phase 12
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Kalyan
  • Village Titwala
  • Original Completion 30 November 2024
  • Revised Completion 30 November 2024
  • Project Area (in Sq.mt.) 13,060.0
  • Total Buildings/Towers 2
  • Documents 34 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 15 July 2021 Expected commencement of civil works and foundation on site.
Original Completion 30 November 2024 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 November 2024 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name REGENCY NIRMAN LTD
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Regency CrestRegency Crest Plot no 40 Sector 19 Kharghar Navi Mumbai - 410 2107000CompletedIndustrial21422014-06-302014-12-10NoNA
Regency HeightsNr Brahmand Phase-1 AzadNagar Kolshet Road Thane W - 40060727335.9CompletedIndustrial43202015-03-152015-03-31NoNA
Regency ClassicSurvey NO 54 Hissa no 4 Mumbai Bangalore Highway Near Mahindra Showroom Baner Pune-41104512400CompletedIndustrial31322015-10-312016-03-28NoNA
Regency WillowsPlot no 61 Green Valley Behind Fariyas Hotel Tungari Lonavala19858CompletedIndustrial24242014-02-032014-02-03NoNA
Regency Sarvam Phase 1Gupta Estates Near Titwala Railway Station Ganpati Mandir Road Titwala E - 421605.23488.32CompletedIndustrial53502013-10-312014-03-21NoNA
Regency Sarvam Phase 2Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 42160526247.81CompletedIndustrial64242015-03-312015-08-20NoNA
Regency Sarvam Phase 3Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 42160530909.13CompletedIndustrial65522015-03-312015-12-16NoNA
Regency Sarvam Phase 4Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 42160513676.03CompletedIndustrial32342016-04-302016-06-09NoNA
Regency Sarvam Phase 5Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 42160510079.23CompletedIndustrial21342016-12-312017-02-10NoNA
Regency Sarvam Phase 6Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 42160516890.79CompletedIndustrial32712017-05-032017-05-03NoNA
Regency Sarvam Phase 7Gupta Estates Near Titwala Railway Station Ganpati Mandir road Titwala E - 42160516890.9CompletedIndustrial32712017-05-312017-07-18NoNA

Promoters, Co-promoters & Members

NameRoleAddress
MAHESH SATYANARAYAN KHAIRARIManaging DirectorThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Regency Sarvam Phase 12 Building No 40 0 0 25 0 0 NA
Regency Sarvam Phase 12 Commercial Building No 3 0 0 1 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 200
Configurations 3
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 138 units · avg area 38.35 Sq.mt.
2 BHK 46 units · avg area 56.80 Sq.mt.
Shop 16 units · avg area 21.94 Sq.mt.
  • Building No 40
  • Commercial Building No 3
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 37.64 46 34
1BHK 38.7 92 63
2BHK 56.8 46 42
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 50.0% Street Lighting % not reported
Community Buildings 100.0% Treatment And Disposal Of Sewage And Sullage Water 100.0% Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • Building No 40
  • Commercial Building No 3
Building No 40 · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 1 Building Plan Approval NA Order For Plotted Development.Pdf
6 1 Commencement Certificates NA Order For Plotted Development.Pdf
7 2 Commencement Certificates NA Order For Plotted Development.Pdf
8 1 Declaration About Commencement Certificate.Pdf
9 1 Declaration In FORM B.Pdf
10 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
11 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
12 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
14 1 Disclosure Of Sold Booked Inventory.Pdf
15 2 Disclosure Of Sold Booked Inventory.Pdf
16 3 Disclosure Of Sold Booked Inventory.Pdf
17 4 Disclosure Of Sold Booked Inventory.Pdf
18 5 Disclosure Of Sold Booked Inventory.Pdf
19 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
20 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
21 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
22 2 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
23 1 Proforma Of Allotment Letter.Pdf
24 2 Proforma Of Allotment Letter.Pdf
25 1 Other – Technical.Pdf
26 2 Other – Technical.Pdf
27 1 Architect’S Certificate On Completion Of Project (Form 4).Pdf
28 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
29 2 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
30 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
31 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
32 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank SARASWAT COOPERATIVE BANK LIMITED
IFSC SRCB0000281
Branch Address Vikhroli
Country/City