Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Under Construction Source: rera.mh

Sai Jagdamba CHS RERA Details - P51700076819, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Sai Jagdamba CHS under registration P51700076819 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700076819
  • Project Name JAGDAMBA CO OP HOUSING SOCIETY LTD
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 31 December 2027
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 468.16
  • Total Buildings/Towers 1
  • Documents 38 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 28 June 2024 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2027 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SAI CONSTRUCTION

Promoters, Co-promoters & Members

NameRoleAddress
VISHWANATH BHAGWAN MOREPartnerThane, MAHARASHTRA
RAJKUMAR SITARAM MAHTOPartnerThane, MAHARASHTRA
VINOD HIRJI PATELPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
JAGDAMBA CO OP HOUSING SOCIETY LTD JAGDAMBA CO OP HOUSING SOCIETY LTD 8 28 8 1 1 31 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 31
Configurations 6
Inventory Type RESIDENTIAL
Configuration Distribution
1RK 5 units · avg area 23.16 Sq.mt.
1 RK TO TENANT 2 units · avg area 23.16 Sq.mt.
1 BHK 14 units · avg area 34.91 Sq.mt.
2 BHK 7 units · avg area 45.13 Sq.mt.
Shop 1 unit · avg area 10.35 Sq.mt.
SHOP TO TENANT 2 units · avg area 11.38 Sq.mt.
  • JAGDAMBA CO OP HOUSING SOCIETY LTD
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1RK 23.16 5 0
Shop 10.35 1 0
1 RK TO TENANT 23.16 2 1
2BHK FLAT TO TENANT 45.69 3 0
SHOP TO TENANT 8.61 1 0
SHOP TO TENANT 14.16 1 0
1BHK FLAT TO TENANT 33.99 3 0
1BHK FLAT TO TENANT 35.29 2 0
2BHK FLAT TO TENANT 41.8 1 0
1BHK FLAT TO TENANT 39.09 1 0
2BHK 45.69 3 0
1BHK 35.29 4 0
1BHK 33.99 4 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • JAGDAMBA CO OP HOUSING SOCIETY LTD
JAGDAMBA CO OP HOUSING SOCIETY LTD · Overall Progress 42%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 A Details Of Encumbrances Concerned To Finance.Pdf
4 2 A Details Of Encumbrances Concerned To Finance.Pdf
5 1 B Details Of Encumbrances Concerned To Legal.Pdf
6 2 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 1 Building Plan Approval NA Order For Plotted Development.Pdf
9 1 Commencement Certificates NA Order For Plotted Development.Pdf
10 1 Declaration About Commencement Certificate.Pdf
11 1 Declaration In FORM B.Pdf
12 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
13 1 CERSAI Details.Pdf
14 2 CERSAI Details.Pdf
15 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
16 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
17 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
18 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
19 4 Disclosure Of Interest In Other Real Estate Organizations.Pdf
20 1 Proforma Of Allotment Letter.Pdf
21 1 Proforma Of Agreement For Sale.Pdf
22 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
23 1 Deviation Report With Respect To Allotment Letter.Pdf
24 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
25 1 Other – Legal.Pdf
26 2 Other – Legal.Pdf
27 1 Other – Technical.Pdf
29 2 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
30 3 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
32 2 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
33 3 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
34 4 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
35 5 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
36 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
37 2 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
38 3 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank IDBI BANK
IFSC IBKL0000661
Branch Address Bahar Apartment, B Wing, 955-970, Ground Floor, Gandhi Chowk, Badlapur East 421503
Country/City