Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential New Launch Source: rera.mh

SK Saurabh Sankul RERA Details - P51700081080, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for SK Saurabh Sankul under registration P51700081080 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700081080
  • Project Name SAURABH SANKUL
  • Project Type Others
  • Project Status New Launch
  • State Maharashtra
  • District Thane
  • Taluka Ambarnath
  • Village Badlapur (M Cl)
  • Original Completion 31 December 2028
  • Revised Completion 31 December 2028
  • Project Area (in Sq.mt.) 585.29
  • Total Buildings/Towers 1
  • Documents 40 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 02 January 2026 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2028 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2028 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name S K DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
SURENDRA SAMARU YADAVPartnerThane, MAHARASHTRA
MUKESH SUKHLAL JAINPartnerThane, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SAURABH SANKUL SAURABH SANKUL 44 18 8 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 50
Configurations 6
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 18 units · avg area 31.90 Sq.mt.
Rehab unit 1 RK 3 units · avg area 25.51 Sq.mt.
1RK 9 units · avg area 26.69 Sq.mt.
2 BHK 11 units · avg area 41.44 Sq.mt.
Rehab unit Shop 6 units · avg area 15.37 Sq.mt.
Shop 3 units · avg area 8.66 Sq.mt.
  • SAURABH SANKUL
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
Rehab unit 2 BHK 44.45 3 0
Rehab unit 1 BHK 27.42 2 0
Rehab unit 2 BHK 38.94 3 0
2BHK 44.45 2 0
Rehab unit Shop 10.2 1 0
Rehab unit Shop 26.53 1 0
Rehab unit Shop 13.59 1 0
Rehab unit Shop 16.32 1 0
Rehab unit Shop 14.47 1 0
Rehab unit 1 BHK 34.47 3 0
Rehab unit 1 RK 28.84 1 0
Rehab unit Shop 11.09 1 0
Rehab unit 1 RK 23.84 2 0
Shop 8.16 1 0
1RK 23.84 3 0
1RK 24.52 1 0
1RK 28.84 5 0
1BHK 27.42 4 0
Shop 8.91 2 0
1BHK 33.78 5 0
1BHK 33.94 1 0
1BHK 34.47 3 0
2BHK 38.94 3 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • SAURABH SANKUL
SAURABH SANKUL · Overall Progress 0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 A Details Of Encumbrances Concerned To Finance.Pdf
5 2 A Details Of Encumbrances Concerned To Finance.Pdf
6 1 Copy Of Layout Approval (In Case Of Layout).Pdf
7 1 Proforma Of Allotment Letter.Pdf
8 1 Declaration In FORM B.Pdf
9 1 Architect’S Certificate Of Percentage Of Completion Of Work (Form 1).Pdf
10 1 CA Certificate On Project Cost & Fund Withdrawal (Form 3).Pdf
11 1 Engineer’S Certificate On Cost Incurred On Project (Form 2).Pdf
12 1 Commencement Certificates NA Order For Plotted Development.Pdf
13 1 Building Plan Approval NA Order For Plotted Development.Pdf
14 2 Building Plan Approval NA Order For Plotted Development.Pdf
15 3 Building Plan Approval NA Order For Plotted Development.Pdf
16 4 Building Plan Approval NA Order For Plotted Development.Pdf
17 5 Building Plan Approval NA Order For Plotted Development.Pdf
18 6 Building Plan Approval NA Order For Plotted Development.Pdf
19 4 Other – Legal.Pdf
20 2 Other – Legal.Pdf
21 1 Other – Legal.Pdf
22 3 Other – Legal.Pdf
23 1 Declaration About Commencement Certificate.Pdf
24 1 CERSAI Details.Pdf
25 1 Declaration About All RERA Designated Bank Accounts (Format A).Pdf
26 1 Deviation Report With Respect To Allotment Letter.Pdf
27 1 B Details Of Encumbrances Concerned To Legal.Pdf
28 2 B Details Of Encumbrances Concerned To Legal.Pdf
29 2 Other – Finance.Pdf
30 1 Other – Finance.Pdf
31 1 Other – Technical.Pdf
32 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
33 1 Proforma Of Agreement For Sale.Pdf
34 1 Disclosure Of Interest In Other Real Estate Organizations.Pdf
35 2 Disclosure Of Interest In Other Real Estate Organizations.Pdf
36 3 Disclosure Of Interest In Other Real Estate Organizations.Pdf
37 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
38 1 Disclosure For Secured Unsecured Finance Availed For The Project.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF BARODA
IFSC BARB0TISGAO
Branch Address Karina plaza Building Near Santoshi Mata Man Kalyan 421306