RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700011047
  • Project Name TIRUPATI COMPLEX
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Mira-Bhayandar (M Corp.)
  • Original Completion 30 December 2022
  • Revised Completion 31 December 2027
  • Project Area (in Sq.mt.) 635.22
  • Total Buildings/Towers 1
  • Documents 80 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 31 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2022 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2027 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name TIRUPATI DEVELOPERS

Promoters, Co-promoters & Members

NameRoleAddress
DIMPLE PRAKASH SHAHPartnerThane, MAHARASHTRA
KAILASH KUMAR SANGHVIPartnerThane, MAHARASHTRA
LATA R MUTHAPartnerThane, MAHARASHTRA
SANGEETHA P SANGHVIPartnerThane, MAHARASHTRA
SANTOSH KANWAR SHAHPartnerThane, MAHARASHTRA
UTTAM R SHAHPartnerThane, MAHARASHTRA
VIPUL S JAINPartnerThane, MAHARASHTRA
PRAVEEN UKCHAND SANGHVIPartnerThane, MAHARASHTRA
Location

Land, Address & Location Details

Land parcel, zoning and geo-coordinates as recorded in the project filing.

Address CTpAhCposdbSxHpwedCwwyRufofCKB0BWg4UzRQmsqAaWABLGeEmKjLDWZgjPhxJ

RERA Coordinates

Latitude, Longitude 19.311208000000001, 72.851472999999999

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
TIRUPATI COMPLEX TIRUPATI COMPLEX BLDG 2 C AND D WING 124 1 6 6 6 40 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 40
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 20 units · avg area 42.93 Sq.mt.
2 BHK 20 units · avg area 65.42 Sq.mt.
  • TIRUPATI COMPLEX BLDG 2 C AND D WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
1BHK 40.89 1 1
2BHK 60.31 1 1
1BHK 44.01 9 8
2BHK 66.66 9 5
2BHK 64.82 10 5
1BHK 42.17 10 5
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 100.0% Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • TIRUPATI COMPLEX BLDG 2 C AND D WING
TIRUPATI COMPLEX BLDG 2 C AND D WING · Overall Progress 91%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

40 3 Certificates Of CA (Form 3).Pdf
Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 2 Copy Of The Legal Title Report.Pdf
4 1 Details Of Encumbrances.Pdf
5 2 A Details Of Encumbrances Concerned To Finance.Pdf
6 1 B Details Of Encumbrances Concerned To Legal.Pdf
7 1 Copy Of Layout Approval (In Case Of Layout).Pdf
8 2 Copy Of Layout Approval (In Case Of Layout).Pdf
9 1 Building Plan Approval (IOD).Pdf
10 2 Building Plan Approval (IOD).Pdf
11 3 Building Plan Approval (IOD).Pdf
12 1 Commencement Certificates NA Order For Plotted Development.Pdf
13 2 Commencement Certificates NA Order For Plotted Development.Pdf
14 1 Declaration About Commencement Certificate.Pdf
15 2 Declaration About Commencement Certificate.Pdf
16 1 Declaration In FORM B.Pdf
17 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
18 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
19 3 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
20 4 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
21 5 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
22 6 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
23 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
24 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
25 3 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
26 4 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
27 5 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
28 1 Form 2A.Pdf
29 1 Engineers Certificate On Quality Assurance (Form 2A FY 2020 21).Pdf
30 1 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
31 2 Engineers Certificate On Quality Assurance (Form 2A FY 2021 22).Pdf
32 1 Engineers Certificate On Quality Assurance (Form 2A FY 2022 23).Pdf
33 1 Disclosure Of Sold Booked Inventory.Pdf
34 1 CERSAI Details.Pdf
35 2 Disclosure Of Sold Booked Inventory.Pdf
36 3 Disclosure Of Sold Booked Inventory.Pdf
37 4 Disclosure Of Sold Booked Inventory.Pdf
38 1 Certificates Of CA (Form 3).Pdf
39 2 Certificates Of CA (Form 3).Pdf
41 4 Certificates Of CA (Form 3).Pdf
42 5 Certificates Of CA (Form 3).Pdf
43 6 Certificates Of CA (Form 3).Pdf
44 7 Certificates Of CA (Form 3).Pdf
45 1 Certificates Of CA (Form 5).Pdf
46 2 Certificates Of CA (Form 5).Pdf
47 3 Certificates Of CA (Form 5).Pdf
48 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
49 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
50 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
51 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2021 22).Pdf
52 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2022 23).Pdf
53 1 Proforma Of Allotment Letter.Pdf
54 2 Proforma Of Allotment Letter.Pdf
55 1 Proforma Of Agreement For Sale.Pdf
56 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2023 24).Pdf
57 1 Separate Bank Account Details Including No Encumbrances On The Bank Account Or No Escrow On The Same.Pdf
58 1 Letter From The Bank Regarding The Opening Of RERA Designated Bank Accounts (Format B).Pdf
59 1 Deviation Report With Respect To Allotment Letter.Pdf
60 1 Deviation Report With Respect To Model Copy Of Agreement.Pdf
61 1 Other.Pdf
62 2 Other.Pdf
63 1 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
72 2 Engineers Certificate On Quality Assurance (Form 2A FY 2023 24).Pdf
73 Withdrawal Update Form 1.Pdf
79 Withdrawal Update Form 2.Pdf
85 Withdrawal Update Form 3.Pdf
91 Form 2A (FY 2025 2026).Pdf
92 Form 2A (FY 2024 2025).Pdf
93 Form 5 (FY 2018 2019).Pdf
94 Form 5 (FY 2019 2020).Pdf
95 Form 5 (FY 2020 2021).Pdf
96 Form 5 (FY 2021 2022).Pdf
97 Form 5 (FY 2022 2023).Pdf
98 Form 5 (FY 2023 2024).Pdf
99 Form 5 (FY 2024 2025).Pdf
100 Form 5 (FY 2025 2026).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank UNION BANK OF INDIA
IFSC UBIN0539287
Branch Address BHAYANDER WEST THANE 401101
Country/City