Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Unique Skyline II MHADA RERA Details - P51700003362, Thane

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Unique Skyline II MHADA under registration P51700003362 in Thane, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P51700003362
  • Project Name SKYLINE-II
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Thane
  • Taluka Thane
  • Village Mira-Bhayandar (M Corp.)
  • Original Completion 30 June 2018
  • Revised Completion 30 September 2018
  • Project Area (in Sq.mt.) 1,806.75
  • Total Buildings/Towers 2
  • Documents 33 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 05 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 September 2018 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Others
Individule Name UNIQUE SHANTI NEMINATH DEVELOPERS LLP

Promoters, Co-promoters & Members

NameAddress
HEMAL J DOSHIMumbai Suburban, MAHARASHTRA
DILESH SHAHMumbai City, MAHARASHTRA
KUNAL S DOSHIMumbai Suburban, MAHARASHTRA
MADHU H DOSHIMumbai Suburban, MAHARASHTRA
UNIQUE SHANTI DEVELOPERS LLPMumbai Suburban, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SKYLINE-II B-WING 0 52 19 0 0 NA
SKYLINE-II C-WING 0 52 20 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 256
Configurations 2
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 126 units · avg area 37.37 Sq.mt.
2 BHK 130 units · avg area 53.24 Sq.mt.
  • B-WING
  • C-WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2BHK 53.24 64 36
1BHK 36.76 32 29
1BHK 38.02 30 30
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) 25.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 25.0% Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water 25.0% Solid Waste Management And Disposal 50.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 90.0%
Electrical Meter Room, Sub-station, Receiving Station 90.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • B-WING
  • C-WING
B-WING · Overall Progress 89%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work80%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
1 1 PAN Card.Pdf
2 1 Copy Of The Legal Title Report.Pdf
3 1 Details Of Encumbrances.Pdf
4 1 Copy Of Layout Approval (In Case Of Layout).Pdf
5 2 Copy Of Layout Approval (In Case Of Layout).Pdf
6 3 Copy Of Layout Approval (In Case Of Layout).Pdf
7 4 Copy Of Layout Approval (In Case Of Layout).Pdf
8 5 Copy Of Layout Approval (In Case Of Layout).Pdf
9 6 Copy Of Layout Approval (In Case Of Layout).Pdf
10 7 Copy Of Layout Approval (In Case Of Layout).Pdf
11 8 Copy Of Layout Approval (In Case Of Layout).Pdf
12 9 Copy Of Layout Approval (In Case Of Layout).Pdf
13 1 Building Plan Approval (IOD).Pdf
14 1 Commencement Certificates NA Order For Plotted Development.Pdf
15 1 Declaration In FORM B.Pdf
16 1 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
17 2 Certificates Of Architect (Form 1)(Mandatory For Only Ongoing Project).Pdf
18 1 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
19 2 Certificates Of Engineer (Form 2)(Mandatory For Only Ongoing Project).Pdf
20 1 Certificates Of CA (Form 3).Pdf
21 2 Certificates Of CA (Form 3).Pdf
22 1 Certificates Of CA (Form 5).Pdf
23 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2018 19).Pdf
24 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2019 20).Pdf
25 1 Annual Audit Report Of Statutory CA (Form 5) (FY 2020 21).Pdf
26 1 Proforma Of Allotment Letter.Pdf
27 2 Proforma Of Allotment Letter.Pdf
28 1 Occupancy Certificate Completion Certificate Architect'S Certificate Of Completion For Plotted Development.Pdf
29 1 Architect’S Certificate On Completion Of Project (Form 4).Pdf
30 2 Architect’S Certificate On Completion Of Project (Form 4).Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank YES BANK
IFSC YESB0000214
Branch Address SHOP NO 3/4 OFFICE NO 29/A NIRMAL NAGAR, SAI BABA NAGAR MIRA BHAYANDER, MIRA ROAD EAST- THANE- 40110
Country/City