Bhojwani HI Face RERA Details - P52100004321, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Bhojwani HI Face under registration P52100004321 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100004321
  • Project Name Hi Face
  • Project Type Others
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Pimpale Saudagar
  • Original Completion 31 October 2018
  • Revised Completion 30 October 2021
  • Project Area (in Sq.mt.) 7,450.0
  • Total Buildings/Towers 4
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 09 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 31 October 2018 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 October 2021 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name MBM Developers

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Hi Face A Building 16 10 9 0 0 NA
Hi Face B Building 21 21 9 0 0 NA
Hi Face C Building 28 19 7 0 0 NA
Hi Face D Building 0 5 3 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 91
Configurations 5
Inventory Type RESIDENTIAL
Configuration Distribution
1 BHK 6 units · avg area 35.43 Sq.mt.
2 BHK 79 units · avg area 54.08 Sq.mt.
3 BHK 1 unit · avg area 75.75 Sq.mt.
Office 1 unit · avg area 222.70 Sq.mt.
Shop 4 units · avg area 10.15 Sq.mt.
  • A Building
  • B Building
  • C Building
  • D Building
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
3 BHK 75.75 1 1
2 BHK 51.52 3 3
1 BHK 35.43 6 6
2 BHK 36.04 1 1
2 BHK 36.07 6 5
2 BHK 49.55 6 6
2 BHK 51.47 3 3
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 50.0% Water Supply 30.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 30.0%
Storm Water Drains 50.0% Landscaping & Tree Planting 60.0% Street Lighting 60.0%
Community Buildings 40.0% Treatment And Disposal Of Sewage And Sullage Water 20.0% Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting 40.0% Energy Managemcnt 40.0% Fire Protection And Fire Safety Requirements 50.0%
Electrical Meter Room, Sub-station, Receiving Station 38.0% Aggregate Area Of Recreational Open Space 40.0% Open Parking 50.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A Building
  • B Building
  • C Building
  • D Building
A Building · Overall Progress 69%
Plinth
Complete
% Work100%
Stilt Floor
In Progress
% Work80%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work50%
Sanitary Fittings within the flats / premises
In Progress
% Work50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work20%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank BANK OF MAHARASHTRA
IFSC MAHB0001443
Branch Address Dwarka lords Pimple saudagar Pune 411027
Country/City