residential Ready to Move Source: rera.mh

Clover Highlands RERA Details - P52100005703, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Clover Highlands under registration P52100005703 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100005703
  • Project Name CLOVER HIGHLANDS
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village kondhwa khurd
  • Original Completion 30 December 2026
  • Revised Completion 30 December 2026
  • Project Area (in Sq.mt.) 71,000.0
  • Total Buildings/Towers 2
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 11 August 2017 Expected commencement of civil works and foundation on site.
Original Completion 30 December 2026 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 December 2026 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Clover Developers Pvt Ltd
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Clover HiglandsNibm road71000CompletedResidential / Group Housing264462007-03-312007-03-31NoNA

Promoters, Co-promoters & Members

NameRoleAddress
DHIREN POPATLAL NANDUDIRECTOR Pune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
CLOVER HIGHLANDS WING 8 10 195 26 22 (G + 21) 21 84 NA
CLOVER HIGHLANDS WING 9 9 182 26 22 (G + 21) 21 84 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 99.0% Water Supply 98.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 99.0%
Storm Water Drains 99.0% Landscaping & Tree Planting 99.0% Street Lighting 99.0%
Community Buildings 98.0% Treatment And Disposal Of Sewage And Sullage Water 99.0% Solid Waste Management And Disposal 99.0%
Water Conservation /Rain Water Harvesting 99.0% Energy Managemcnt 10.0% Fire Protection And Fire Safety Requirements 99.0%
Electrical Meter Room, Sub-station, Receiving Station 99.0% Aggregate Area Of Recreational Open Space 100.0% Open Parking 99.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • WING 8
  • WING 9
WING 8 · Overall Progress 99%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work99%
Sanitary Fittings within the flats / premises
In Progress
% Work98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
In Progress
% Work99%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
116 Withdrawal Update Form 1.Pdf
117 Withdrawal Update Form 2.Pdf
118 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank HDFC BANK
IFSC HDFC0000148
Branch Address PUNE CAMP
Country/City