residential Ready to Move Source: rera.mh

Goel Ganga Liviano RERA Details - P52100018256, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Goel Ganga Liviano under registration P52100018256 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100018256
  • Project Name SHRINIWAS LIVIANO PHASE I
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Pune City
  • Original Completion 30 September 2020
  • Revised Completion 30 March 2021
  • Project Area (in Sq.mt.) 17,184.3
  • Total Buildings/Towers 4
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 17 October 2018 Expected commencement of civil works and foundation on site.
Original Completion 30 September 2020 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 30 March 2021 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name GOEL GANGA LANDMARKS LLP

Promoters, Co-promoters & Members

NameRoleAddressEmail
SWARANSINGH GYANSINGH SOHALPartnerPune, MAHARASHTRA-
GOEL GANGA SPACE LLP though its Partner Subhash GoelPartnerPune, MAHARASHTRAW527XLxZcLETsDPG70RhFyVKxMKmvllsbzPQGFwFMEAIIsva1pnOQxDauWjy7lim

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
SHRINIWAS LIVIANO PHASE I A WING 36 98 17 0 0 NA
SHRINIWAS LIVIANO PHASE I B WING 14 64 16 0 0 NA
SHRINIWAS LIVIANO PHASE I C WING 18 61 16 0 0 NA
SHRINIWAS LIVIANO PHASE I D WING 18 83 16 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 212
Configurations 4
Inventory Type RESIDENTIAL
Configuration Distribution
2 BHK 68 units · avg area 72.71 Sq.mt.
3 BHK 56 units · avg area 104.99 Sq.mt.
4 BHK 24 units · avg area 143.07 Sq.mt.
5 BHK 64 units · avg area 82.95 Sq.mt.
  • A WING
  • B WING
  • C WING
  • D WING
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
4 BHK 146.45 1 0
3 BHK 102.91 14 0
4 BHK 139.35 3 0
3 BHK 102.52 1 0
3 BHK 127.23 2 0
4 BHK 147.1 1 0
3 BHK 102.94 12 0
4 BHK 146.97 4 0
4 BHK 139.3 3 0
4 BHK 146.57 6 0
4 BHK 139.58 1 0
4 BHK 139.22 1 0
3 BHK 119.8 2 0
4 BHK 139.54 4 0
2 BHK 89.3 1 0
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 95.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting 50.0% Street Lighting 50.0%
Community Buildings 60.0% Treatment And Disposal Of Sewage And Sullage Water 50.0% Solid Waste Management And Disposal 70.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 60.0% Aggregate Area Of Recreational Open Space 60.0% Open Parking 80.0%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A WING
  • B WING
  • C WING
  • D WING
A WING · Overall Progress 93%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work75%
Sanitary Fittings within the flats / premises
In Progress
% Work72%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
In Progress
% Work91%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
In Progress
% Work90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0006488
Branch Address MG ROAD BRANCH PUNE CAMP PUNE
Country/City