RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100047921
- Project Name Life Republic Sector R13/13th Avenue/Aros/Phase I
- Project Type Others
- Project Status Under Construction
- State Maharashtra
- District Pune
- Taluka Mulshi
- Village Nere
- Original Completion 31 December 2026
- Revised Completion 31 December 2026
- Project Area (in Sq.mt.) 9,203.59
- Total Buildings/Towers 5
- Documents 5 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
Land, Address & Location Details
Land parcel, zoning and geo-coordinates as recorded in the project filing.
| Survey Number 26/5P, 26/6P, 69/1P, 69/2/1P, 69/2/2P, 69/2/3P, 69/2/4P, 69/2/5P, 69/2/6P, 69/2/7P, 69/2/8P | |
Boundary Details |
|
| Boundaries East 18 M Internal Road and R10 | Boundaries West Township boundary s no 69P and 110M RP Road |
| Boundaries South 18 M internal road and Sector R12 | Boundaries North Township boundary s no 26P and MSEB switching stat |
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads & Footpaths 80.0% | Water Supply 30.0% | Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0% |
| Storm Water Drains 100.0% | Landscaping & Tree Planting 30.0% | Street Lighting 40.0% |
| Community Buildings 85.0% | Treatment And Disposal Of Sewage And Sullage Water 100.0% | Solid Waste Management And Disposal 100.0% |
| Water Conservation /Rain Water Harvesting 100.0% | Energy Managemcnt 90.0% | Fire Protection And Fire Safety Requirements 100.0% |
| Electrical Meter Room, Sub-station, Receiving Station 95.0% | Aggregate Area Of Recreational Open Space 100.0% | Open Parking 95.0% |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
RERA Documents & Filings