residential Ready to Move Source: rera.mh

Kotibhaskar Prabhakar CHSL RERA Details - P52100049315, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kotibhaskar Prabhakar CHSL under registration P52100049315 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100049315
  • Project Name PRABHAKAR CHSL
  • Project Type Residential / Group Housing
  • Project Status Ready to Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Karve Nagar
  • Original Completion 12 July 2025
  • Revised Completion 12 July 2025
  • Project Area (in Sq.mt.) 460.0
  • Total Buildings/Towers 1
  • Documents 3 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 07 February 2023 Expected commencement of civil works and foundation on site.
Original Completion 12 July 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 12 July 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Kotibhaskar Infrastructures &Developers Pvt.Ltd.
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Snehvardhan Co-operative Housing SocietyPatwardhan Co-operative Housing Society928.4CompletedResidential / Group Housing1202017-05-232017-01-20NoNA
Chinar Co-operative Housing SocietyKothrud Pune1300CompletedResidential / Group Housing1242014-03-312014-03-25NoNA
Ankoorshree Co-operative Housing SocietyHappy Colony Lane 3 Kothrud Pune968CompletedResidential / Group Housing1212017-10-222017-05-25NoNA
AnnapurnaHingane Budruk Haveli Pune339.21CompletedResidential / Group Housing152017-12-202017-06-22NoNA

Promoters, Co-promoters & Members

NameRoleAddress
Dilip Shivanand KotibhaskarManaging DirectorPune, MAHARASHTRA
Chidambar Shivanand kotibhaskarChairpersonPune, MAHARASHTRA
Chidambar Shivanand kotibhaskarChairpersonPune, MAHARASHTRA
Dilip Shivanand KotibhaskarManaging DirectorPune, MAHARASHTRA
Chidambar Shivanand kotibhaskarChairpersonPune, MAHARASHTRA
Dilip Shivanand KotibhaskarManaging DirectorPune, MAHARASHTRA
Chidambar Shivanand kotibhaskarChairpersonPune, MAHARASHTRA
Dilip Shivanand KotibhaskarManaging DirectorPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors No. of Habitable Floor No. of Sanctioned Apartment Wing Name
PRABHAKAR CHSL PRABHAKAR CHSL 0 22 8 0 0 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt 100.0% Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • PRABHAKAR CHSL
PRABHAKAR CHSL · Overall Progress 55%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
95 Occupational Certificate.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
IFSC SBIN0001110
Branch Address SHIROLE BHAVAN, PMT BUILDING, PUNE