residential Partially Ready To Move Source: rera.mh

Kumar Prithvi RERA Details - PR1262022501312, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Kumar Prithvi under registration PR1262022501312 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PR1262022501312
  • Project Name Prithvi - H3
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Kondhwa Khurd – EXT
  • Original Completion 25 April 2031
  • Revised Completion 25 April 2031
  • Project Area (in Sq.mt.) 47,800.0
  • Total Buildings/Towers 2
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 20 October 2025 Expected commencement of civil works and foundation on site.
Original Completion 25 April 2031 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 25 April 2031 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name Sukumar Township Development Private Limited
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
Kumar Prithvi Ph 1Survey No 45-46 Kondhwa Main road Market yard Road Annnex Kondhwa Pune11427.03CompletedResidential / Group Housing82642013-10-192013-10-19NoNA
Prithvi - H1Survey No 45-46 Kondhwa Main Road Market yard Road Annnex Kondhwa Pune5602.13CompletedResidential / Group Housing11022018-07-222018-03-28NoNA
Prithvi - H245, 46, Dr APJ Abdul Kalam Road, Mallik Nagar, kondhwa khurd, Haveli, Pune, 411048, MAHARASHTRA6546.54OngoingResidential / Group Housing12027-04-30NoNA

Promoters, Co-promoters & Members

NameRoleAddress
Kewalkumar Kesarimal JainDirectorPune, MAHARASHTRA
Hitesh JainDirectorPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
Prithvi - H3 H3-Wing A 0 252 21 21 18 72 NA
Prithvi - H3 H3-Wing B 0 252 21 21 18 72 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 80.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 98.0%
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • H3-Wing A
  • H3-Wing B
H3-Wing A · Overall Progress 44%
Stilt Floor
Complete
% Work100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Not Started
% Work0%
Plinth
Complete
% Work100%
Slabs of Super Structure
In Progress
% Work35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
In Progress
% Work5%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Withdrawal Update Form 1.Pdf
3 Withdrawal Update Form 2.Pdf
5 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
IFSC SBIN0004726
Branch Address TARA.CHAMBERS,NEAR.MARIYAI,POLICE.CHOWKY,MUMBAIPUNE.ROAD
Country/City