Squareyards Logo
Blogs
Sell or Rent Property
Login
Rera Banner
residential Ready to Move Source: rera.mh

Pashankar Yin Yang RERA Details - P52100021750, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Pashankar Yin Yang under registration P52100021750 in Pune, MAHARASHTRA. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100021750
  • Project Name Yin Yang
  • Project Type Residential
  • Project Status Ready to Move
  • State MAHARASHTRA
  • District Pune
  • Taluka Pune City
  • Village Pune (M Corp.)
  • Original Completion 31 December 2019
  • Project Area (in Sq.mt.) 707.46
  • Total Buildings/Towers 2
  • Documents 16 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 23 July 2019 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2019 Mandated date for project handover to the allottees and final compliance filing.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name Proxima Creations
Other Description NA

Promoters, Co-promoters & Members

NameRole
Gautam Vishwanand PashankarAuthorized Signatory

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name Date of Completion No. of Basements No. of Plinth No. of Podium No. of Slab No. of Slits No. of Open Parking No. of Closed Parking
Yin Yang A Wing 2019-12-31 2 1 1 3 0 0 0
Yin Yang C Wing 2019-12-31 2 0 1 3 0 0 0

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Inventory

Unit Inventory & Configuration Details

Configuration mix and floor-level disclosures with both grouped and raw RERA views.

Total Units 6
Configurations 1
Inventory Type RESIDENTIAL
Configuration Distribution
5 BHK 6 units · avg area 155.30 Sq.mt.
  • A Wing
  • C Wing
Floor-Wise Inventory Explorer
Apartment Type Carpet Area No. of Apartment No. of Booked Apartment
2.5BHK 126.05 2 0
2.5BHK 119.69 2 0
Parking

Parking, Garage & Area Details

Parking provision declared in the sanctioned plan.

Type Proposed Booked Work Done
Garage NA NA 0
Covered Parking 14 0 100
Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads Footpaths 80% Water Conservation Rainwater Harvesting 80% Energy Management 80%
Fire Protection And Fire Safety Requirements 80% Electrical Meter Room Substation Receivingstation 80% Aggregate Area Of Recreational Open Space % not reported
Open Parking % not reported Water Supply % not reported Sewerage 80%
Storm Water Drains 80% Landscaping Tree Planting 28% Street Lighting 80%
Community Buildings 80% Treatment And Disposal Of Sewage Sullage Water % not reported Solid Waste Management Disposal 80%
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • A Wing
  • C Wing
A Wing · Overall Progress 87%
Excavation
Complete
% Work100%
X number of Basement(s) and Plinth
Complete
% Work100%
X number of Podiums
Complete
% Work100%
Stilt Floor
Not Started
% Work0%
X number of Slabs of Super Structure
Complete
% Work100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Complete
% Work100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
In Progress
% Work66%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Complete
% Work100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Complete
% Work100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Details Html
Mh Certificate Pdf
Mh Details Pdf
1 Copy Of The Legal Title Report
1 Details Of Encumbrances
2 Details Of Encumbrances
3 Details Of Encumbrances
4 Details Of Encumbrances
5 Details Of Encumbrances
1 Copy Of Layout Approval (In Case Of Layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order For Plotted Development
1 Declaration In FORM B
1 Proforma Of Allotment Letter
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank Indian Bank
IFSC IDIB000T027
Country/City