RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100004143
- Project Name PRAKRUTI PALLADIUM
- Project Type Others
- Project Status Ready to Move
- State MAHARASHTRA
- District Pune
- Taluka Haveli
- Village kondhwa BK
- Original Completion 31 March 2019
- Revised Completion 31 December 2019
- Project Area (in Sq.mt.) 4,487.4
- Total Buildings/Towers 1
- Documents 38 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 32 | 0 | 50 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 10% | Water Conservation Rainwater Harvesting 00% | Energy Management 00% |
| Fire Protection And Fire Safety Requirements 00% | Electrical Meter Room Substation Receivingstation 00% | Aggregate Area Of Recreational Open Space 00% |
| Open Parking % not reported | Water Supply 10% | Sewerage 00% |
| Storm Water Drains 00% | Landscaping Tree Planting 00% | Street Lighting 00% |
| Community Buildings 00% | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | ORIENTAL BANK OF COMMERCE |
|---|---|
| IFSC | ORBC0100986 |