residential Under Construction Source: rera.mh

Rohan Harita RERA Details - PR1263032501085, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for Rohan Harita under registration PR1263032501085 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number PR1263032501085
  • Project Name ROHAN HARITA PHASE 3
  • Project Type Residential / Group Housing
  • Project Status Under Construction
  • State Maharashtra
  • District Pune
  • Taluka Mulshi
  • Village Tathwade
  • Original Completion 31 December 2029
  • Revised Completion 31 December 2029
  • Project Area (in Sq.mt.) 34,700.0
  • Total Buildings/Towers 1
  • Documents 5 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 01 October 2025 Expected commencement of civil works and foundation on site.
Original Completion 31 December 2029 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 31 December 2029 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Company
Individule Name ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
ROHAN KRITIKA WINGS A CCTS 538 A PARVATI PUNE CITY 4110054200CompletedResidential / Group Housing21032018-09-302018-12-31NoNA
ROHAN LEHER 2 WING ASNo 53-5 53-6 P 54-1 P 54-12 Baner Pune 411045435.48CompletedResidential / Group Housing1442019-09-302019-09-30NoNA
ROHAN LEHER 2 WING B C DESNo 53-5 53-6 P 54-1 P 54-12 Baner Pune 4110451312CompletedResidential / Group Housing3372018-09-302018-09-30NoNA
ROHAN LEHER 2 WING F G H I JSNO 53-5 53-6P 54-12 54-1P BANER PUNE-4110451603CompletedResidential / Group Housing5502017-06-302017-06-30NoNA
ROHAN ISHAN WING A 5 TO 11 FLOORSNO 9-2 9-3 BAVDHAN BK TALUKA MULSHI PUNE 411021848.51CompletedResidential / Group Housing1412017-06-302017-06-30NoNA
ROHAN ABHILASHA BUILDING AGAT NO 1458 1459 1460P 1461 1462 1463 1464 1465 WAGHOLI Pune-4122078573.7CompletedResidential / Group Housing6842017-11-302017-11-30NoNA
ROHAN ABHILASHA BUILDING CCTS 538 A PARVATI Pune4200CompletedResidential / Group Housing21032018-09-302018-09-30NoNA
ROHAN ABHILASHA BUILDING EGAT NO 1458 1459 1460 P 1461 1462 1463 1464 1465 WAGHOLI Pune- 4122075723.22CompletedResidential / Group Housing43302018-06-302018-06-30NoNA
ROHAN ABHILASHA BUILDING FGAT NO 1458 1459 1460 P 1461 1462 1463 1464 1465 WAGHOLI Pune- 4122075327.68CompletedResidential / Group Housing33302019-06-302019-06-30NoNA
ROHAN LEHER IIIS NO 60-1 60-2P 60-2-1 60-3P BANER Pune-4110453109.75CompletedResidential / Group Housing12062021-06-302021-06-30NoNA

Promoters, Co-promoters & Members

NameRoleAddress
SANJAY KHUSHALCHAND LUNKADDirectorPune, MAHARASHTRA
DEEPAK KACHARDAS BHATEWARADirectorPune, MAHARASHTRA
MILIND KHUSHALCHAND LUNKADDirectorPune, MAHARASHTRA
SUHAS KHUSHALCHAND LUNKADDirectorPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
ROHAN HARITA PHASE 3 J WING 128 39 39 32 145 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths % not reported Water Supply % not reported Sewerage (Chamber, Lines, Septic Tank , Stp) % not reported
Storm Water Drains % not reported Landscaping & Tree Planting % not reported Street Lighting % not reported
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal % not reported
Water Conservation /Rain Water Harvesting % not reported Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements % not reported
Electrical Meter Room, Sub-station, Receiving Station % not reported Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • J WING
J WING · Overall Progress 0%
Excavation
Not Started
% Work0%
Basement (if any)
Not Started
% Work0%
Podiums (if any)
Not Started
% Work0%
Plinth
Not Started
% Work0%
Stilt Floor
Not Started
% Work0%
Slabs of Super Structure
Not Started
% Work0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Not Started
% Work0%
Sanitary Fittings within the flats / premises
Not Started
% Work0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Not Started
% Work0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Not Started
% Work0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Not Started
% Work0%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Details Html
1 Withdrawal Update Form 1.Pdf
3 Withdrawal Update Form 2.Pdf
5 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank ICICI BANK LIMITED
IFSC ICIC0000039
Branch Address ICICI Bank Ltd., 1194/8, Ramchandra Sabhamandap, Ghole Road , Shivaji Nagar, Pune.411005