RERA Snapshot
The most important statutory project disclosures, generated dynamically from available RERA fields.
- RERA Number P52100005459
- Project Name ARYAN LANDMARK
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Pune
- Taluka Haveli
- Village Pimpri Chinchawad (M Corp.)
- Original Completion 31 July 2019
- Revised Completion 31 July 2019
- Project Area (in Sq.mt.) 2,333
- Total Buildings/Towers 2
- Documents 33 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| NANDKUMAR SHANTARAM JADHAV | Partner |
| ANIL VASANT CHAVAN | Partner |
| SANDEEP RAM PAWALE | Partner |
| SAGAR BABANRAO MARNE | Authorized Signatory |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| ARYAN LANDMARK | A BUILDING | 2019-07-31 | 0 | 1 | 0 | 6 | 1 | 22 | 0 |
| ARYAN LANDMARK | B BUILDING | 2019-07-31 | 0 | 1 | 0 | 6 | 0 | 22 | 0 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- A BUILDING
- B BUILDING
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| 2BHK | 47.39 | 1 | 1 |
| 2BHK | 47.49 | 2 | 2 |
| 2BHK | 49.7 | 1 | 1 |
| 2BHK | 49.9 | 1 | 1 |
| 2BHK | 53.41 | 1 | 1 |
| 2BHK | 53.43 | 1 | 1 |
| 2BHK | 53.6 | 1 | 1 |
| 2BHK | 53.62 | 2 | 2 |
| 2BHK | 54.18 | 1 | 1 |
| 2BHK | 56.02 | 4 | 4 |
| 2BHK | 56.2 | 2 | 2 |
| 2BHK | 56.22 | 3 | 3 |
| 1BHK | 36.15 | 1 | 1 |
| 1BHK | 37.53 | 1 | 1 |
| 1BHK | 37.9 | 1 | 1 |
| 1BHK | 37.91 | 2 | 2 |
| 2BHK | 46.54 | 1 | 1 |
| 2BHK | 46.56 | 2 | 2 |
| 2BHK | 46.63 | 2 | 2 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 22 | 6 | 40 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths % not reported | Water Conservation Rainwater Harvesting 100% | Energy Management 100% |
| Fire Protection And Fire Safety Requirements 100% | Electrical Meter Room Substation Receivingstation 100% | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking 12% | Water Supply 100% | Sewerage 100% |
| Storm Water Drains 100% | Landscaping Tree Planting 100% | Street Lighting % not reported |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- A BUILDING
- B BUILDING
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | IDBI BANK |
|---|---|
| IFSC | IBKL0000087 |