residential Partially Ready To Move Source: rera.mh

The Silver Altair RERA Details - P52100049673, Pune

View the RERA registration, promoter, approval, building, inventory, document and construction-progress disclosures for The Silver Altair under registration P52100049673 in Pune, Maharashtra. Data is sourced from rera.mh.

RERA

RERA Snapshot

The most important statutory project disclosures, generated dynamically from available RERA fields.

  • RERA Number P52100049673
  • Project Name THE SILVER ALTAIR TOWER-D MHADA
  • Project Type Residential / Group Housing
  • Project Status Partially Ready To Move
  • State Maharashtra
  • District Pune
  • Taluka Haveli
  • Village Ravet
  • Original Completion 30 June 2025
  • Revised Completion 28 July 2025
  • Project Area (in Sq.mt.) 363.86
  • Total Buildings/Towers 1
  • Documents 6 Verified
Timeline

Project Timeline & Completion Details

Key statutory dates from registration through proposed completion and permit validity.

Proposed Start 22 February 2023 Expected commencement of civil works and foundation on site.
Original Completion 30 June 2025 Mandated date for project handover to the allottees and final compliance filing.
Revised Completion 28 July 2025 No revision filed against the original committed handover date.
Promoter

Promoter, Organisation & Member Details

Declared promoter entity, address and corporate identifiers on file with the authority.

Organisation Type Partnership
Individule Name SILVER STAR GROUP
Experience Details
Project NameAddressLand AreaProject StatusType of ProjectBuild Plot CountApartment countProposed Completion DateProject End DateLitigation PresentLitigation Details
RUTUGANDHS NO 141 BEHIND GURUDHAWARA NEAR AKURDI RLY STATION CHINCHWAD925.57CompletedResidential / Group Housing1322016-08-312017-06-02NoNA

Promoters, Co-promoters & Members

NameRoleAddress
DEVIDAS RAMCHANDRA VANJARIPartnerPune, MAHARASHTRA

Understand this Project's RERA details

Get clear answers and additional support from our RERA experts.

RERA Banner
Buildings

Buildings, Towers & Building-Level Details

Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.

Building Detail
Project Name Name No. of Open Parking No. of Closed Parking No. of Floors CC Issued No. of Habitable Floor No. of Sanctioned Apartment Wing Name
THE SILVER ALTAIR TOWER-D MHADA THE SILVER ALTAIR TOWER-D MHADA 0 23 16 16 12 48 NA

Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.

Development

Development Works & Common Area Disclosures

Project-level common infrastructure disclosures as reported by the developer to the RERA authority.

Internal Roads & Footpaths 100.0% Water Supply 100.0% Sewerage (Chamber, Lines, Septic Tank , Stp) 100.0%
Storm Water Drains 100.0% Landscaping & Tree Planting % not reported Street Lighting 100.0%
Community Buildings % not reported Treatment And Disposal Of Sewage And Sullage Water % not reported Solid Waste Management And Disposal 100.0%
Water Conservation /Rain Water Harvesting 100.0% Energy Managemcnt % not reported Fire Protection And Fire Safety Requirements 100.0%
Electrical Meter Room, Sub-station, Receiving Station 100.0% Aggregate Area Of Recreational Open Space % not reported Open Parking % not reported
Activity

Building Activity Progress

Statutory activity-wise construction progress as declared by the developer, per building/tower.

  • THE SILVER ALTAIR TOWER-D MHADA
THE SILVER ALTAIR TOWER-D MHADA · Overall Progress 100%
Excavation
Complete
% Work100%
Basement (if any)
Complete
% Work100%
Podiums (if any)
Complete
% Work100%
Plinth
Complete
% Work100%
Stilt Floor
Complete
% Work100%
Slabs of Super Structure
Complete
% Work100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Complete
% Work100%
Sanitary Fittings within the flats / premises
Complete
% Work100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Complete
% Work100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Complete
% Work100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Complete
% Work100%
Documents

RERA Documents & Filings

All statutory documents uploaded by the promoter to the authority portal.

Mh Certificate Pdf
Mh Extension Certificate Pdf
Mh Details Html
57 Withdrawal Update Form 1.Pdf
59 Withdrawal Update Form 2.Pdf
61 Withdrawal Update Form 3.Pdf
Bank

Bank & Cost Disclosure

Declared project cost and the designated escrow account on file.

Project Account Bank STATE BANK OF INDIA
IFSC SBIN0004726
Branch Address GODREJ CASTLEMINE OFF NO-2 BUND GARDEN ROAD PUNE STATION