- RERA Number P51700005877
- Project Name PRASADAM PHASE III
- Project Type Residential
- Project Status Ready to Move
- State MAHARASHTRA
- District Thane
- Taluka Ambarnath
- Village Ambarnath(M Cl)
- Original Completion 31 May 2016
- Revised Completion 21 December 2021
- Project Area (in Sq.mt.) 5,489.47
- Total Buildings/Towers 1
- Documents 104 Verified
Project Timeline & Completion Details
Key statutory dates from registration through proposed completion and permit validity.
Promoter, Organisation & Member Details
Declared promoter entity, address and corporate identifiers on file with the authority.
Promoters, Co-promoters & Members
| Name | Role |
|---|---|
| Jia Zhuowen Wei | Director |
Understand this Project's RERA details
Get clear answers and additional support from our RERA experts.
Buildings, Towers & Building-Level Details
Statutory building-level disclosures including tower height, sanctioned floors, structural counts and parking areas.
| Project Name | Name | Date of Completion | No. of Basements | No. of Plinth | No. of Podium | No. of Slab | No. of Slits | No. of Open Parking | No. of Closed Parking |
|---|---|---|---|---|---|---|---|---|---|
| PRASADAM PHASE III | PRASADAM WING NOPQ | 2020-12-21 | 0 | 1 | 0 | 8 | 1 | 0 | 40 |
Scroll horizontally to view all building-level fields. Values marked "-" were not disclosed in the source RERA record.
Unit Inventory & Configuration Details
Configuration mix and floor-level disclosures with both grouped and raw RERA views.
- PRASADAM WING NOPQ
| Apartment Type | Carpet Area | No. of Apartment | No. of Booked Apartment |
|---|---|---|---|
| Shop | 16.41 | 1 | 1 |
| SHOP14 | 45.56 | 1 | 1 |
| SHOP16 | 33.32 | 1 | 1 |
| Shop | 41.04 | 1 | 1 |
| Shop | 35.49 | 1 | 1 |
| SHOP7 | 23.25 | 5 | 5 |
| 1BHK | 35.75 | 58 | 57 |
| Shop | 47.64 | 3 | 1 |
| 3BHK | 66.32 | 8 | 6 |
| 2BHK | 50.21 | 6 | 6 |
| 2BHK | 52.89 | 8 | 8 |
| Shop | 54.16 | 1 | 0 |
| 3BHK | 67.08 | 6 | 6 |
| Shop | 74.22 | 1 | 0 |
| Shop | 26.49 | 1 | 0 |
| Shop | 30.42 | 1 | 0 |
| Shop | 34.53 | 1 | 0 |
| 1BHK | 35.27 | 3 | 0 |
| Shop | 35.52 | 1 | 0 |
| 1BHK | 35.77 | 1 | 0 |
| 1BHK | 35.80 | 12 | 11 |
| 1BHK | 35.95 | 12 | 12 |
| Shop | 47.66 | 2 | 0 |
Parking, Garage & Area Details
Parking provision declared in the sanctioned plan.
| Type | Proposed | Booked | Work Done |
|---|---|---|---|
| Garage | 0 | 0 | 0 |
| Covered Parking | 40 | 0 | 0 |
Development Works & Common Area Disclosures
Project-level common infrastructure disclosures as reported by the developer to the RERA authority.
| Internal Roads Footpaths 75% | Water Conservation Rainwater Harvesting % not reported | Energy Management % not reported |
| Fire Protection And Fire Safety Requirements % not reported | Electrical Meter Room Substation Receivingstation % not reported | Aggregate Area Of Recreational Open Space % not reported |
| Open Parking 100% | Water Supply % not reported | Sewerage % not reported |
| Storm Water Drains 80% | Landscaping Tree Planting 50% | Street Lighting 50% |
| Community Buildings % not reported | Treatment And Disposal Of Sewage Sullage Water % not reported | Solid Waste Management Disposal % not reported |
Building Activity Progress
Statutory activity-wise construction progress as declared by the developer, per building/tower.
- PRASADAM WING NOPQ
RERA Documents & Filings
All statutory documents uploaded by the promoter to the authority portal.
Bank & Cost Disclosure
Declared project cost and the designated escrow account on file.
| Project Account Bank | HDFC BANK LTD |
|---|---|
| IFSC | HDFC0000079 |